Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

PSM-I Professional Scrum Master I Questions and Answers

Questions 4

If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?

Options:

A.

The evolution of the cost spent on the project.

B.

When all work will be completed to the Scrum Team can be released for other work.

C.

When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team.

D.

When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.

Buy Now
Questions 5

Which of the following are true about the length of the Sprint? (Choose two.)

Options:

A.

The length of the Sprint should be proportional to the work that is done in between Sprints.

B.

It is best to have Sprints of consistent length throughout a development effort.

C.

Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.

E.

All Sprints must be 1 month or less.

Buy Now
Questions 6

Who should make sure everyone on the Development Team does their tasks for the Sprint?

Options:

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

E.

All of the above.

Buy Now
Questions 7

A new Developer is having continuing conflicts with existing members or the scrum Team, which is impacting the delivery of the Increment It necessary, who is responsible for removing the Developer from the Scrum Team?

(choose the best answer)

Options:

A.

The Scrum Master is responsible, they remove impediments

B.

The Product Owner is responsible, they control the return on investment (ROI)

C.

The hiring manager is responsible, they hired the Developer

D.

The Scrum Team is responsible

Buy Now
Questions 8

When does a Sprint conclude?

(choose the best answer)

Options:

A.

When the Product Owner decides enough has been delivered to meet the Sprint

Goal.

B.

When the Sprint Retrospective is complete.

C.

When all the tasks are completed by the Developers.

D.

When all Product Backlog items meet their Definition of Done.

Buy Now
Questions 9

What does n mean tor a scrum Team to be cross-function at? (choose the best answer)

Options:

A.

The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint

B.

Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team

C.

The Scrum Team includes not only developers but also business analysts, architects, and testers

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers

Buy Now
Questions 10

True or False: The purpose of a Sprint Is lo produce a valuable useful Inclement.

Options:

A.

True

B.

False

Buy Now
Questions 11

What is the key concern when multiple Development Teams are working from the same Product Backlog?

Options:

A.

Minimizing dependencies between teams.

B.

Clear definition of requirements.

C.

Meeting original scope projections.

D.

Making sure there’s enough work for everyone on every team.

E.

Maximizing velocity.

Buy Now
Questions 12

Every Scrum Team must have a Product Owner and Scrum Master. (Choose the best answer.)

Options:

A.

True. Outcomes affected by their participation and availability.

B.

False. A Product Owner can be replaced by a subject matter expert in the Scrum Team.

C.

False. A Scrum Master is only required when asked for by the Scrum Team.

D.

True. Each must be 100% dedicated to the Scrum Team.

Buy Now
Questions 13

The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.

Options:

A.

True

B.

False

Buy Now
Questions 14

When is a Product Backlog item considered complete? (choose the best answer)

Options:

A.

When the item passes ail acceptance criteria

B.

When the item has gamed product sponsor approval

C.

At the end of the Sprint

D.

When the item meets the Definition of Done

Buy Now
Questions 15

Who owns the Sprint Backlog?

Options:

A.

The Scrum Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

Buy Now
Questions 16

How should a Development Team deal with non-functional requirements?

Options:

A.

Ensure every Increment meets them.

B.

Make sure the release department understands these requirements, but it is not the Development Team’s responsibility.

C.

Handle them during the Integration Sprint preceding the Release Sprint.

D.

Assign them to the lead developers on the team.

Buy Now
Questions 17

Which three of the following are true about Scrum? (Choose the best three answers.)

Options:

A.

Scrum implements self-management by replacing Project Managers with Scrum Masters.

B.

Each component of Scrum serves a specific purpose and is essential to Scrum’s success and your usage

of Scrum to develop complex products.

C.

Scrum is a methodology where you can pick and choose which parts of Scrum you think will work for your

environment.

D.

Scrum is a framework for developing and sustaining complex products.

E.

Scrum is based on empiricism and lean thinking.

Buy Now
Questions 18

What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?

Options:

A.

There are no such activities. The next Sprint starts immediately after the current Sprint.

B.

Refine the Product Backlog.

C.

Work with the Quality Assurance departments on the Increment of the current Sprint.

D.

Update the project plan with stakeholders.

Buy Now
Questions 19

Who is responsible for tracking the remaining work of the Sprint?

Options:

A.

The Development Team.

B.

The Scrum Master.

C.

The Project Manager.

D.

The Development Team is consultation with the Product Owner.

E.

The Product Owner.

Buy Now
Questions 20

When multiple Scrum Teams are working on a single product, what best describes the

Definition of Done?

(choose the best answer)

Options:

A.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.

B.

Each Scrum Team defines and uses its own. The differences are discussed and

reconciled during a hardening Sprint.

C.

Each Scrum Team uses its own, but must make their definition clear to all other

teams so the differences are known.

D.

The Scrum Masters from each Scrum Team define a common Definition of Done.

Buy Now
Questions 21

What is the typical size for a Scrum Team?

(choose the best answer)

Options:

A.

7 plus or minus 3.

B.

At least 7.

C.

9

D.

10 or fewer.

Buy Now
Questions 22

Which three behaviors demonstrate that a team is self-organizing? (Choose three.)

Options:

A.

Stakeholders walking in at the Daily Scrum to check progress and work with the Scrum Master to optimize the functional scope for the Sprint.

B.

The Development Team members are working within the boundaries of their functional description and nicely handing off work from analyst to developer to tester to integration.

C.

The Product Owner doesn’t need to be at Sprint Retrospectives.

D.

The Development Team creating their own sprint backlog, reflecting all work that is part of the definition of “Done”.

E.

The Development Team has all the skills needed to create a releasable Increment.

F.

Development Team members collaboratively selecting their own work during the Sprint.

G.

The Development Team inviting external people to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.

Buy Now
Questions 23

Which statement best describes Scrum?

(choose the best answer)

Options:

A.

A defined and predictive process that conforms to the principles of Scientific

Management

B.

A framework to generate value through adaptive solutions tor complex problems.

C.

A cookbook that defines best practices tor software development.

D.

A complete methodology that defines how to develop software.

Buy Now
Questions 24

Which two of the following are true about the Scrum Master role? (Choose two.)

Options:

A.

At the Sprint Review, the Scrum Master identifies what has been “done” and what has not been “done”.

B.

The Scrum Master teaches the Development Team to keep the Scrum meetings to their time-box.

C.

The Scrum Master helps those outside the team interact with the Scrum Team.

D.

The Scrum Master assigns tasks to Development Team members when they need work.

E.

The Scrum Master is responsible for updating the Sprint Burndown.

Buy Now
Questions 25

Which answer best describes the topics covered in Sprint Planning? (Choose the best answer.)

Options:

A.

What to do and who will do it.

B.

How conditions have changed and how the Product Backlog should evolve.

C.

What can be done and how to do it, and why to do it.

D.

What went wrong in the last Sprint and what to do differently this Sprint.

E.

Who is on the team and what team member roles will be.

Buy Now
Questions 26

When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint'

(choose the best answer)

Options:

A.

Never The entire Scrum Team is accountable for creating value every Sprint.

B.

At the Sprint Planning Evented

C.

Whenever a team member can accommodate more worn.

D.

During the Daily scrum

Buy Now
Questions 27

Who should know the most about the progress toward a business objective or a release?

Options:

A.

The Project Manager.

B.

The Scrum Master.

C.

The Development Team.

D.

The Product Owner.

Buy Now
Questions 28

The Product Owner must release each Increment to production.

Options:

A.

When it makes sense.

B.

To make sure the Development Team is done every Sprint.

C.

Whenever the product is free of defects.

D.

Without exception.

Buy Now
Questions 29

When do Development Team members take ownership of a Sprint Backlog item?

Options:

A.

At the Sprint planning meeting.

B.

During the Daily Scrum.

C.

Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.

D.

Whenever a team member can accommodate more work.

Buy Now
Questions 30

What does it mean for a Development Team to be cross-functional?

Options:

A.

The Development Team includes not only developers but also business analysts, architects, and testers.

B.

The Development Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of software.

C.

Developers on the Development Team work closely with business analysts, architects, developers and testers who are not on the team.

D.

The Development Team is a virtual team drawing from separate teams of business analysts, architects, developers and testers.

Buy Now
Questions 31

Who is responsible for managing the progress of work during a Sprint?

Options:

A.

The Scrum Master.

B.

The Development Team.

C.

The Product Owner.

D.

The most junior member of the Team.

Buy Now
Questions 32

In accordance with Scrum theory, how should a group of 100 people be divided into multiple Development Teams?

Options:

A.

Understanding the product, the product vision and the rules of the Scrum framework, the group divides itself into teams.

B.

It doesn’t really matter because you can rotate the teams every Sprint to spread knowledge.

C.

Check with the allocation department to see who has worked together before and make these the first teams.

D.

Create a matrix of skills, seniority, and level of experience to assign people to teams.

Buy Now
Questions 33

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

Options:

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Development Team's plan for the Sprint.

E.

It is ordered by the Product Owner.

Buy Now
Questions 34

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

Options:

A.

Release Planning.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Buy Now
Questions 35

Which of these may a Development Team deliver at the end of a Sprint?

Options:

A.

Failing unit tests, to identify acceptance tests for the next Sprint.

B.

An increment of software with minor known bugs in it.

C.

An increment of working software that is “done”.

D.

A single document, if that is what the Scrum Master asked for.

Buy Now
Questions 36

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

Options:

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

Buy Now
Questions 37

Which of the following are roles on a Scrum Team? (Choose all that apply.)

Options:

A.

Users

B.

Scrum Master

C.

Product Owner

D.

Development Team

E.

Customers

Buy Now
Questions 38

At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of “Done”. What two things should happen with the undone Product Backlog item? (Choose two.)

Options:

A.

If the stakeholders agree, the Product Owner can accept it and release it to the users.

B.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

C.

Review the item, add the “Done” part of the estimate to the velocity and create a Story for the remaining work.

D.

Do not include the item in the Increment this Sprint.

Buy Now
Questions 39

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

Options:

A.

There should be six Product Owners, one tor each Scrum Team.

B.

There should be six Product Owners, reporting to a Chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Buy Now
Questions 40

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

Options:

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Buy Now
Questions 41

Who has the final decision about the order of items in the Product Backlog? (Choose the best answer.)

Options:

A.

The Stakeholders.

B.

The Product Owner.

C.

The Scrum Team.

D.

The Scrum Master.

E.

The Developers.

Buy Now
Questions 42

Which three of the following are time-boxed events in Scrum? (Choose three.)

Options:

A.

Release Testing.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Buy Now
Questions 43

The Product Backlog is ordered by:

Options:

A.

The Product Owner with the most valuable items placed at the top.

B.

Risk, where safer items are at the top, and riskier items are at the bottom.

C.

Items are randomly arranged.

D.

Size, where small items ale at the top and large items are at the bottom.

Buy Now
Questions 44

What is the time-box for the Sprint Planning meeting?

Options:

A.

4 Hours for a monthly Sprint.

B.

8 Hours for a monthly Sprint.

C.

Monthly.

D.

Whenever it is done.

Buy Now
Questions 45

When does the next Sprint begin?

Options:

A.

When the Product Owner is ready.

B.

Immediately after the conclusion of the previous Sprint.

C.

The Monday following the Sprint Review.

D.

Immediately following the next Sprint Planning.

Buy Now
Questions 46

During the Sprint. Me Scrum Master's role is to do which two of the following: (choose the best two answers)

Options:

A.

Facilitate inspection and adaptation opportunities as requested or needed

B.

Coaching the team members in self-management

C.

Ensure the Product Owner attends all scrum events.

D.

Escalate team conflicts to functional line managers

E.

Monitor the progress of the Developers

F.

Assign tasks with the Scrum team.

Buy Now
Questions 47

A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component. Without that component there won’t be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help. What would be good advice to give the Product Owner?

Options:

A.

Remind the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog.

B.

Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.

C.

Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Development Team.

Buy Now
Questions 48

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)

Options:

A.

There should be six Product Owners, one for each Scrum Team.

B.

There should be six Product Owners, reporting to a chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Buy Now
Questions 49

True or False: Multiple scrum Teams working on the same product must have the same Sprint start date.

Options:

A.

True

B.

False

Buy Now
Questions 50

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

Options:

A.

Its productivity is likely to decrease.

B.

Its productivity is likely to stay the same.

C.

Its productivity is likely to increase.

Buy Now
Questions 51

Which three purposes does the definition of “Done” serve? (Choose three.)

Options:

A.

Guide the Development Team on how many Product Backlog items to select for the Sprint.

B.

Create a shared understanding of when work is complete.

C.

Describe the purpose, objecti ve, and time-box of each Scrum event.

D.

Describe the work that must be done before the Sprint is allowed to end.

E.

Increase transparency.

Buy Now
Questions 52

When is the Sprint Backlog created?

Options:

A.

At the beginning of the project.

B.

During the Sprint Planning meeting.

C.

Prior to the Sprint Planning meeting.

D.

During the Sprint.

Buy Now
Questions 53

What happens if the Development Team cannot complete its work by the end of the Sprint?

Options:

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Buy Now
Questions 54

Which two things should the Scrum Team do during the first Sprint?

(choose the best two answers)

Options:

A.

Define the major product features and a release plan architecture.

B.

Build at least one piece of valuable functionality.

C.

Create at least one valuable, useful Increment

D.

Make up a plan tor the rest of the project

E.

Analyze, describe, and document the requirements for the subsequent Sprints.

Buy Now
Questions 55

What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)

Options:

A.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

B.

Add security concerns to the definition of “Done”.

C.

Add a Sprint to specifically resolve all security concerns.

D.

Delegate the work to the concerned department.

E.

Have the Scrum Team create Product Backlog items for each concern.

Buy Now
Questions 56

A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?

Options:

A.

Call a meeting between the Development Team and senior management.

B.

Comply with the decision of the self-organizing team.

C.

Consult with the Product Owner to see how he/she feels about the situation.

D.

Begin facilitating productive and useful Sprint Retrospectives.

Buy Now
Questions 57

Why does the Product Owner want the Development Team to adhere to its definition of “Done”?

Options:

A.

To have complete transparency into what has been done at the end of each Sprint.

B.

To be able to reprimand the team when they don’t meet their velocity goal for the Sprint.

C.

To know what the team will deliver over the next three Sprints.

D.

To predict the team’s productivity over time.

Buy Now
Questions 58

Which statement best describes the Sprint Backlog as the output ot the Sprint Planning?

(choose the best answer)

Options:

A.

Every item nas a designated owner.

B.

It is ordered by the Product Owner.

C.

Each task is estimated in hours.

D.

It is the Developers plan for the Sprint

E.

It is a complete list of all work to be done in a Sprint.

Buy Now
Questions 59

During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)

Options:

A.

Consider the request and decide on which days the Daily Scrum should occur.

B.

Coach the team on why the Daily Scrum is important as an opportunity to update the plan.

C.

Have the developers vote.

D.

Learn why the Development Team wants this and work with them to improve the outcome of the Daily Scrum.

E.

Acknowledge and support the self-organizing team’s decision.

Buy Now
Questions 60

How often should Development Team membership change?

Options:

A.

As needed, while taking into account a short term reduction in productivity.

B.

Never, because it reduces productivity.

C.

As needed, with no special allowance for changes in productivity.

D.

Every Sprint to promote shared learning.

Buy Now
Questions 61

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Options:

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Buy Now
Questions 62

Every Development Team should have:

Options:

A.

At least one representative from each major software engineering discipline (like QA, Dev, UX).

B.

The competencies and skills needed to deliver a Done Increment in a Sprint.

C.

One Lead Developer and no more than 8 other members.

Buy Now
Questions 63

You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)

Options:

A.

Introduce a bonus system for the top performers in the team.

B.

Have the Scrum Team members introduce themselves to each other and give a brief background of their skills and work history.

C.

Have the development managers for each Development Team member introduce their direct reports and go over their responsibilities on the Scrum Team.

D.

Ensure the Scrum Team members have compatible personalities.

E.

Ensure the team understands they need a definition of “Done”.

F.

Ask the Product Owner to discuss the product or project, its history, goals, and context, as well as answer questions.

Buy Now
Questions 64

For which is the Scrum Master responsible?

Options:

A.

Managing the performance of the Scrum Team.

B.

The meetings and the objectives that a Scrum Team sets for itself.

C.

The Scrum framework being adopted and used properly.

D.

Keeping track of resource allocation.

Buy Now
Questions 65

Who must attend the Daily Scrum?

Options:

A.

The Scrum Master and Product Owner.

B.

The Development Team.

C.

The Development Team and Product Owner.

D.

The Scrum Team.

E.

The Development Team and Scrum Master.

Buy Now
Questions 66

Which of the following is a Developer accountable for? (Choose the best two answers.)

Options:

A.

Selecting the Product Owner.

B.

Reporting productivity.

C.

Creating a plan for the Sprint, the Sprint Backlog.

D.

Organizing the work required to meet the Sprint Goal.

Buy Now
Questions 67

A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?

Options:

A.

The hiring manager is responsible, because he/she hired the developer.

B.

The Scrum Manager is responsible, because he/she removes Impediments.

C.

The Development Team is responsible, and may need help from the Scrum Master.

D.

The Product Owner is responsible, because he/she controls the return on investment (ROI).

Buy Now
Questions 68

What is the tactic a Scrum Master should use to divide a group of 100 people into multiple Development Teams?

Options:

A.

Create teams based on their skills across multiple layers (such as database, UI, etc.)

B.

Ask the Product Owner to assign the people to teams.

C.

Ask the developers to divide themselves into teams.

Buy Now
Questions 69

Which Scrum Value is affected by a lack of trust in the Scrum Team?

Options:

A.

Focus

B.

Respect

C.

Openness

D.

Courage

E.

Commitment.

F.

All of the above

Buy Now
Questions 70

What is included in the Sprint Backlog?

Options:

A.

User Stories.

B.

Tasks.

C.

Use Cases.

D.

Tests.

E.

Any of the above (or others) which are a decomposition of the selected Product Backlog items.

Buy Now
Questions 71

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Options:

A.

The Scrum Team.

B.

The Product Owner.

C.

The Developers.

D.

The Project Manager.

Buy Now
Questions 72

When can a Development Team cancel a Sprint?

Options:

A.

It can’t. Only Product Owners can cancel Sprints.

B.

When functional expectations are not well understood.

C.

When the Product Owner is absent too often.

D.

When the selected Product Backlog items for the Sprint become unachievable.

E.

When a technical dependency cannot be resolved.

Buy Now
Questions 73

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)

Options:

A.

Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

B.

It depends.

C.

Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.

D.

All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.

Buy Now
Questions 74

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

Options:

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Development Team’s ability to deliver.

D.

Its Definition of “Done”.

E.

All of the above.

Buy Now
Questions 75

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

(Choose the best answer.)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a

hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

All Scrum Teams must have a Definition of Done that makes their combined work potentially releasable.

Buy Now
Exam Code: PSM-I
Exam Name: Professional Scrum Master I
Last Update: Dec 3, 2024
Questions: 250
PSM-I pdf

PSM-I PDF

$29.75  $84.99
PSM-I Engine

PSM-I Testing Engine

$35  $99.99
PSM-I PDF + Engine

PSM-I PDF + Testing Engine

$47.25  $134.99