PRINCE2 Practitioner Exam
Last Update Dec 27, 2024
Total Questions : 282
Why Choose CramTick
Last Update Dec 27, 2024
Total Questions : 282
Last Update Dec 27, 2024
Total Questions : 282
Customers Passed
PRINCE2 Prince2-Practitioner
Average Score In Real
Exam At Testing Centre
Questions came word by
word from this dump
Try a free demo of our PRINCE2 Prince2-Practitioner PDF and practice exam software before the purchase to get a closer look at practice questions and answers.
We provide up to 3 months of free after-purchase updates so that you get PRINCE2 Prince2-Practitioner practice questions of today and not yesterday.
We have a long list of satisfied customers from multiple countries. Our PRINCE2 Prince2-Practitioner practice questions will certainly assist you to get passing marks on the first attempt.
CramTick offers PRINCE2 Prince2-Practitioner PDF questions, and web-based and desktop practice tests that are consistently updated.
CramTick has a support team to answer your queries 24/7. Contact us if you face login issues, payment, and download issues. We will entertain you as soon as possible.
Thousands of customers passed the PRINCE2 PRINCE2 Practitioner Exam exam by using our product. We ensure that upon using our exam products, you are satisfied.
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Using the Project Scenario answer the following question. The Plan for stage 3 has been approved and work has commenced.
Column 1 contains a number of issues for this project. Select from Column 2 the appropriate category for each issue. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Additional Information
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
Which of the following risk responses can be used for either an opportunity or a threat?