Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Which is one of the six aspects of project performance that needs to be managed?
Who should act as the communication channel between a project and corporate or programme management?
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
When should the Project Board refer to corporate or programme management for a decision?
Which does NOT reflect the PRINCE2 principle of continued business justification?
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
Which is a step in the recommended approach to 'defining and analyzing the products'?
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.
The application of which principle helps to define what should be included in a project?
According to PRINCE2, which characteristic is necessary for an effective project board?
Which should be provided by corporate or programme management before the Starting up a Project process commences?
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?
Identify the missing word in the following sentence.
A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
What must be produced to meet the minimum requirements for applying the change theme?
How does the project board use the 'manage by stages' principle to control the project?
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?
Identify the missing word(s) in the following sentence.
The 'controlling a stage' process is used to manage and control each [ ? ] of a project.
Which management product is used to record relationships between specialist products?
According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?
Identify the missing words in the following sentence.
The 'starting up a project" process is triggered when a [ ? J is available.
What must be produced to meet the minimum requirements when applying the change theme?
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?
Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.
According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?
Which management level should approve a course of action if project-level tolerance is exceeded?
When developing a business case, the project manager reviewed the end project report from & previous similar project that stated had been underestimated on the project.
Which principle is being applied by the project manager when reviewing this information?
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
What statement describes how the project manager should ensure effective communication within a project?
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?
Which term is defined as the measurable threshold to represent the tolerable range of outcomes for each objective ‘at risk’?
The project board needs to review whether the investment remains justified as the project progresses according to plan.
Which principle is being applied by the ‘business case' practice when the project board undertakes this review?
Thea project manager needs to report to the project board on the status of the project's issues.
Which management product should the project manager review?
Which details the identified threats and Opportunities related in the project?
Which plan is used to organize and control the work when executing a work package?
Which TWO are objectives of the 'closing a project’ process?
1. To confirm to the project board that each stage’s products are approved
2. To review whether the project was delivered within time and cost tolerances
3. To confirm whether operational staff are happy to take ownership of the products
4. To confirm that there is authority to close the project
The project manager needs to understand what makes the outputs acceptable to the users.
In which step of the 'planning' technique should this occur?
Which term is defined as the means by which an organization transitions to a desired future state?
According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
According to the guidance for effective quality management, when should the requirements for a product be captured?
Which TWO are objectives of the 'managing a stage boundary" process?
1. To confirm to the project board that there are no products outstanding for the stage
2. To ensure that expectations are managed via accurate reporting to the project manager during a stage
3. To ensure that the project management team is not distracted by delivering additional products during the stage
4. To request the project board to approve work to start on the next stage
Which term is defined as a product that will not meet is quality specifications?
When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
Which common project context relates to the need to engage with external suppliers to deliver part of the project?
The project manager needs to monitor the progress of the stage.
Which combination of management products should the project manager review?
Identify the missing word in the following sentence:
[ ?] is a prediction made by studying historical data and past patterns.
PRINCE2 Certification | Prince2-Foundation Questions Answers | Prince2-Foundation Test Prep | Prince2-Foundation Online Exam | Prince2-Foundation Practice Test | Prince2-Foundation PDF | Prince2-Foundation Test Questions | Prince2-Foundation Study Material | Prince2-Foundation Exam Preparation | Prince2-Foundation Valid Dumps | Prince2-Foundation Real Questions | PRINCE2 Certification Prince2-Foundation Exam Questions