When scheduling performance testing, which of the following approaches would be most advisable? [1]
During what step of the Fundamental Test Process should you define the methods to be used to collect test metrics? [1]
While mining the defect database for patterns of problems in the last release, a Test Manager notices that many of the most damaging failures were caused by defects
injected during the low-level design phase.
Which of the following actions will likely give this project the most effective solution to this problem? [3]
Your last project was released three months ago and used a risk-based approach. In production, a number of serious failures in low risk areas have occurred.
What is the most important lesson to be learned from this information? [2]
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but
it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development
team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be
watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate
for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.
Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]
You are managing a project that will be using a model-based testing strategy.
Which of the following is an activity that will be needed in order to implement this strategy? [1]
Which of the following is a factor that is likely to increase the test estimate? [1]
Which of the following organizational structures would be considered unorthodox? [1]
Which of the following are primary activities in conducting product risk analysis? [1]
You are the Test Manager of a four-person test team working for a small distribution company with a single warehouse. Your team has been working with a third party development team on a new
inventory management system. The company expects this system to generate approximately one million dollars per annum in profits for the company. Early in the project, various risks were
identified, and steps taken to mitigate those risks.
For example, you sent your test team for training on the new system, and upgraded the test environment. There are still some lingering risks that have not been addressed, but they have been
determined to have a low chance of occurring, with minimal impact if they do occur.
What would be the best option to mitigate these remaining risks? [3]
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the
project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,
particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as
"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.
Given this information, which lifecycle model should you recommend?[3]
You are a new Test Manager on a maintenance release for an existing mature product that is expected to be retired in the not too distant
future. The previous release had utilized a performance regression test suite written in an in-house custom tool using the same
programming language as the product itself. This suite will most likely require tweaking to ensure it works with the new version of the
product. While there are several members in the performance testing team, the original author of the performance testing tool has moved on
to another company, and none of the remaining staff have a great deal of familiarity with the performance test scripts used to test this
product.
How would you recommend this scenario be addressed? [3]