Black Friday Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

CTAL-TM Certified Tester Advanced Level Test Manager (CTAL-TM) Questions and Answers

Questions 4

When scheduling performance testing, which of the following approaches would be most advisable? [1]

Options:

A.

Starting the performance testing during unit and integration testing

B.

Deferring the start of performance testing until all functional defects have been resolved

C.

Leveraging end users to do unit-level performance testing and automated tools for system-level performance testing

D.

Requiring all performance tests to pass before starting functional testing

Buy Now
Questions 5

During what step of the Fundamental Test Process should you define the methods to be used to collect test metrics? [1]

Options:

A.

Analysis

B.

Planning

C.

Closure

D.

Execution

Buy Now
Questions 6

While mining the defect database for patterns of problems in the last release, a Test Manager notices that many of the most damaging failures were caused by defects

injected during the low-level design phase.

Which of the following actions will likely give this project the most effective solution to this problem? [3]

Options:

A.

Increased static analysis during the implementation phase

B.

Mandatory reviews of all important design work products

C.

Formal inspections of the code modules affected by the last release

D.

Increased white-box coverage during system testing

Buy Now
Questions 7

Your last project was released three months ago and used a risk-based approach. In production, a number of serious failures in low risk areas have occurred.

What is the most important lesson to be learned from this information? [2]

Options:

A.

The "lessons learned" session should have been conducted prior to deployment.

B.

A broader cross-functional team should contribute to the risk analysis.

C.

The project manager should have set stakeholder expectations for serious failures.

D.

Future projects should test the lower risk areas first.

Buy Now
Questions 8

Which of the following is a key characteristic of a management review? [1]

Options:

A.

Used to assess project risks

B.

Used to check consistency of and deviation from the system requirements

C.

Run by a moderator

D.

Conducted by an external group to assess process compliance

Buy Now
Questions 9

Which testing metric identifies defect density? [1]

Options:

A.

Project

B.

Product

C.

Process

D.

People

Buy Now
Questions 10

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but

it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development

team.

At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be

watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate

for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.

Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]

Options:

A.

Requirements reviews

B.

Test execution

C.

Test monitoring and control

D.

Project management, particularly regarding scheduling and budgeting

Buy Now
Questions 11

You are managing a project that will be using a model-based testing strategy.

Which of the following is an activity that will be needed in order to implement this strategy? [1]

Options:

A.

Conduct a quality risk analysis with all affected stakeholders.

B.

Conduct operational profiling to determine the expected usage of the system.

C.

Select an appropriate quality standard, such as ISO 9126, to be used to guide the testing.

D.

Create the test charters for the exploratory testing sessions.

Buy Now
Questions 12

When, at a minimum, should project risks be re-evaluated? [1]

Options:

A.

Prior to test case creation

B.

At major project milestones

C.

During the creation of the test plan

D.

At the beginning of the test execution phase

Buy Now
Questions 13

Which of the following can demotivate a tester? [1]

Options:

A.

Receiving direct and honest feedback on areas to improve

B.

Working extra hours, resulting in a successful product deployment

C.

When metrics indicate weaknesses in their testing

D.

When testing is cut short, resulting in a high number of production defects

Buy Now
Questions 14

Which of the following is a factor that is likely to increase the test estimate? [1]

Options:

A.

Use of a new technology

B.

A requirement for high level test documentation

C.

Assigned personnel who are experienced on working with similar projects in similar environments

D.

Static test data

Buy Now
Questions 15

Which of the following organizational structures would be considered unorthodox? [1]

Options:

A.

Developers within the same team unit test each others' code prior to handing over to a separate testing team for system testing

B.

Developers and testers are integrated within the same project team, each role focusing on a different level of testing

C.

After developers are done unit testing, business analysts alpha test the system before handing over to a separate testing team for system testing

D.

DBAs confirm the referential integrity of the database and developers complete their unit testing before handing over to

external organization for system testing

Buy Now
Questions 16

Which of the following are primary activities in conducting product risk analysis? [1]

Options:

A.

Risk testing, risk management

B.

Risk identification, risk assessment

C.

Risk identification, risk testing

D.

Risk management, risk assessment

Buy Now
Questions 17

You are the Test Manager of a four-person test team working for a small distribution company with a single warehouse. Your team has been working with a third party development team on a new

inventory management system. The company expects this system to generate approximately one million dollars per annum in profits for the company. Early in the project, various risks were

identified, and steps taken to mitigate those risks.

For example, you sent your test team for training on the new system, and upgraded the test environment. There are still some lingering risks that have not been addressed, but they have been

determined to have a low chance of occurring, with minimal impact if they do occur.

What would be the best option to mitigate these remaining risks? [3]

Options:

A.

Note the risks, and ignore them for now.

B.

Redo the project test plan to add additional testing for these risk items.

C.

Contract with the Risk Protection Insurance company to assume these risks at a cost of $500,000 per annum.

D.

Create a cross-functional team to work to reduce the impact and likelihood of these risks coming to fruition.

Buy Now
Questions 18

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the

project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.

At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,

particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as

"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.

Given this information, which lifecycle model should you recommend?[3]

Options:

A.

Spiral

B.

Iterative/incremental

C.

V-model

D.

Waterfall

Buy Now
Questions 19

You are a new Test Manager on a maintenance release for an existing mature product that is expected to be retired in the not too distant

future. The previous release had utilized a performance regression test suite written in an in-house custom tool using the same

programming language as the product itself. This suite will most likely require tweaking to ensure it works with the new version of the

product. While there are several members in the performance testing team, the original author of the performance testing tool has moved on

to another company, and none of the remaining staff have a great deal of familiarity with the performance test scripts used to test this

product.

How would you recommend this scenario be addressed? [3]

Options:

A.

Retire the in-house tool and switch to a vendor supported tool for performance testing.

B.

Reduce the scope of the product testing to exclude performance testing.

C.

Make the in-house tool available to the open source community.

D.

Leverage the development team to fill any knowledge gaps in the in-house tool.

Buy Now
Exam Code: CTAL-TM
Exam Name: Certified Tester Advanced Level Test Manager (CTAL-TM)
Last Update: Nov 24, 2024
Questions: 65
CTAL-TM pdf

CTAL-TM PDF

$25.5  $84.99
CTAL-TM Engine

CTAL-TM Testing Engine

$30  $99.99
CTAL-TM PDF + Engine

CTAL-TM PDF + Testing Engine

$40.5  $134.99