You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the implementation subject matter expert, the project manager, and the sponsor. Which of these stakeholders will be responsible for writing the project scope?
You are the business analyst for your organization and you're working with the project manager to complete some business analysis activities. The project manager has the authority to approve the requirements based on the short iterations of business analysis activities.
What approach of business analysis are you using in this scenario?
You are the business analyst for your organization and you're working with several stakeholders to identify, manage, and approve requirements. Your organization requires using a plan-driven approach to business analysis and changing management. In this approach, who is most likely to approve changes to requirements?
Business needs do not always originate from the business analyst or from business owners. There are several stakeholders which may identify or contribute to the identification of a business need. Which one of the following stakeholders are most likely to have the most direct awareness of problems that could lead to a business need?
You are the business analyst for your organization. Management has asked you to create a plan that will define the proposed structure and schedule for communicating the business analysis activities to the appropriate stakeholders. What plan does management want you to create?
What's the difference between a desired outcome and a solution? Choose the best answer.
You are the business analyst for a large project for your organization. Your project has 65 stakeholders and this will greatly increase the complexity of the communication in this project. To demonstrate how complex this project and its communication will be, you show the management the number of communication channels in this project. How many channels exist in this project based on the number of stakeholders?
All of the following stakeholders participate in the prioritization of requirements except for which one?
You are working with several business analysts to determine the solution approach for an identified problem. All of the following techniques are acceptable for identifying the solution approach except for which one?
Before requirements can actually be approved to be managed, what must be true about the requirements?
You are the business analyst for your organization. You are currently working with Steve on the organize requirements process. You and Steve have elected to use the user stories approach for this process. What is the user stories approach for requirements organization?
You are the business analyst for your organization. You've believed that your solution can actually be purchased from outside vendor rather than trying to create the solution internally. You decide to ask the vendor to provide a fee for their services based on the statement of work. What document will you give the vendor along with the statement of work?
You're organizing the business analysis approach for your organization. Jane wants to know when changes to requirements are most likely to happen in business analysis processes. Which one of the following statements best describes when changes to requirements may happen?
A business analyst has just hosted a brainstorming session that has generated 57 ideas for a solution. What should the business analyst do with the ideas now?
You are the business analyst for your organization and you're using a plan-driven approach to business analysis processes. In this environment, what types of communications are most likely required to be used in regard to requirements?
You are a Business Analyst for your organization, and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization. Why is it important to complete the plan business analysis approach?
You are the business analyst for an organization and you're managing your stakeholders through the requirements validation activities. Your stakeholders are categorized by executives, functional managers, directors, end users, and customers. Which of these stakeholders are involved in the requirements validation
activities?
As a candidate for CCBA, you should be able to recognize the activities associated with each knowledge area. Which of the following are business analysis planning and monitoring activities? Each correct answer represents a complete solution.
Enterprise analysis creates just five outputs. Which one of the following is an output of the enterprise analysis tasks?
A business analyst has identified four different solutions for a business need. In the light of solution assessment, how many solution assessment iterations should he do?
A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?
Which of the following documents graphically depicts the project team members and displays their interrelationship for a specific project?
All of the following statements are true regarding a brainstorming session during requirements elicitation except for which one?
Complete this statement. Policies and rules serve as boundaries and the organization and the operation of the organization.
High quality requirements have certain characteristics which distinguish them from low-quality requirements. Which characteristic of requirements demands that all requirements in a set or model support its overall purpose and scope?
There are three business analysis planning techniques that a business analyst can use to help plan business analysis processes. Which one of the following is not one of the three techniques?
A business analyst (BA) has determined that “Product Box”, a collaboration game, will provide a fun way to engage the stakeholders when working on prioritizing the list of features. What should the BA do?
When a business analyst is using alternative generation, what should she always include as an output?
Which basis for prioritization allows the project team to work initially with lower-risk requirements first?
If an organization wants to re-use requirements, where should the defined requirements be kept?
Which technique in organizing requirements is best described as showing the concepts and relationships relevant to the solution or business domain?
Beth is a business analyst for her organization and she's completing the tasks in the requirements management and communication knowledge area. As a result of these tasks, she'll create several things for her organization. Which one of the following, however, is not one of the outputs of the requirements management and communication tasks?
By which of the following is the performance of all requirements management and communication activities governed?
A business analyst must consider the business value a solution brings in relation to the cost of implementing the desired solution. Suppliers will often be limited in the amount of requirements they can implement based on the allocated resources. If there are not enough resources to implement all of the solutions, what can the business analyst create to justify the additional funds for the implementation?
You are the business analyst for your organization and you're training Marcy, a new business analyst, on how requirements are formed. Which one of the following best describes how requirements are formed?
Complete this sentence. If a requirement cannot be verified, it cannot be successfully .
You are the business analyst for your organization and you're working with Adam on business analysis processes. Adam is steeped in knowledge regarding the project's purpose. Of the following, what type of business analysis stakeholder is Adam?
A business analyst wants to elicit requirements from a large group of stakeholders. One of her primary goals of this event is to produce a broad set of options for solutions. Which elicitation technique would you recommend for this business analyst?
When using a change-driven approach, the business analyst may create an initial list of high-level requirements for the initiative. This high-level requirements list is also known as what term?
Barry is a project stakeholder that is excited about the deliverable your project wants to create for the organization. He's helpful, provides information, and offers support whenever your project needs it. How would you classify Barry based on this information?
According to the business analysis book 'A Guide to the Business Analysis Body of Knowledge', which your exam is largely based on, almost all methodologies fit somewhere along a spectrum between plan-driven and what other methodology?
Which of the following is used to define and document the business analysis approach?
As a business analyst, you need to define when the activities of the business analysis approach will take place. This includes all of the following business analysis approach activities except for which one?
Which of the following are not appropriate for a plan-driven business analysis approach? Each correct answer represents a complete solution.
Henry is a business analyst in his organization and he's asked an expert to help him determine the best business analysis duties to implement. Why would Henry ask an expert to help him define the business analysis duties?
What does the decomposition of activities and tasks based on the work breakdown structure create for the business analyst?
One of the techniques to assess capabilities in an organization is to use SWOT. What does SWOT accomplish?
You are the business analyst for your organization and you're creating a data flow diagram to show how
information is input, processed, stored, and output from a system. Which element of a data flow diagram represents a process that transforms data by combining it with other data?
A business analyst (BA) is verifying a set of requirements. One of the requirements is “After the customer has received an email confirmation, the customer is likely to access the order status in the order history which is available upon order submission.” Which one of the following requirements quality characteristic is breached?
Which of the following defines all of the required work to satisfy the requirements of the project?
Brian is the business analyst for his organization and he's hosting a brainstorming session. He is facilitating the session with eight stakeholders. Why is it important for Brian to not set a goal for the number of ideas the group should generate in the session?
Which solution scope creation technique can be best described as the depiction of the scope of work required to integrate the new solution into the business and technical environments?
You are the business analyst for your organization and preparing to plan the business analysis approach. There are three inputs to the business analysis approach. Which one of the following is not an input to this approach?
A business analyst has determined that there are five possible solutions to a business need. If the business analyst completes the solution assessment on multiple solutions, what is the goal of the assessment?
You are the business analyst for your organization. You're considering if you should make a solution or purchase it from a vendor. If your team creates the solution, it will cost $286,000 and will cost $2,400 per month to support. The vendor's solution, however, will cost $239,000 and will cost $2,850 per month to support. How long will you need to use your in-house solution to be more cost effective than the vendor's proposed solution?
Billy is the business analyst for her organization and she's working with a team to select a model. Richard doesn't understand why a model is needed for the requirements. Which one of the following statements best describes the reason to use a model?
In order to assess proposed solutions, business analysts will need three inputs. Which one of the following is not an input to the task of assessing proposed solutions?
There are three inputs for stakeholder analysis. Which input describes the existing organizational units and their interactions with one another?
In order to plan the business analysis approach, the business analyst must understand the organizational process needs and what other thing?
Several user groups are impacted by a proposed change to their daily work flow. How should the business analyst (BA) convey these changes so that the user groups understand the impact?
A business analyst (BA) is tasked with developing requirements that can be implemented by the development team iteratively. Which characteristic should the requirements exhibit?
A business analyst (BA) creates several use case scenarios to specify the requirements for a system. When the beta version of the system is released, there are problems because several important pieces of information are missing. What should the BA have done to avoid this situation?
An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?
During the analysis, synthesis, and refinement of elicitation results the business analyst (BA) has discovered that some information is missing. Which course of action would resolve the situation?
A lead business analyst (BA) analyzed the performance of all BA's within the organization. How should the BA approach communicating the results to stakeholders?
A business analyst (BA) worked with two stakeholders to finalize the access rights related requirements for an internal software application. According to the first stakeholder “Comments, once entered in the application, should be stored for 365 days and should not allow the users to delete”. According to the second stakeholder, “The users with super administrator privileges should be able to add/delete/modify every page/section in the entire application.” Which characteristic does this pair of requirements fail to meet?
A business analyst (BA) is eliciting requirements for a pharmaceutical distribution company with an expansion plan across many states, each with their own tools and methods. To make the requirements as re-usable as possible, what should the BA do?
One of the tasks that the business analyst (BA) needs to complete is to maintain the requirements. As much as the BA values and sees the benefits of maintaining the requirements, the project manager (PM) does not see the same. In order to help the PM understand the value of this task, which following benefit of maintaining the requirements should the BA communicate to the PM?
Before beginning requirements elicitation, a business analyst (BA) has planned the necessary activities, identified needed stakeholders, and documented this in the Business Analysis Plan. Which approach will help the BA ensure that stakeholders are available when required?
A business analyst (BA) identified that a stakeholder requirement for an online system led to a functional requirement to provide a user login screen. This is an example of which type of traceability relationship?
A business analyst (BA) is creating a business process model (BPM) showing how the organization will handle errors reported on its website. The BA held a workshop with stakeholders about how the process might work. The BA was also given an instruction manual about a similar error-handling situation, but was advised that some minor aspects are not applicable to the new process. How can the BA use the manual?
A business analyst (BA) is working on a project to provide a temporary solution that will last for two months. The BA is feeling overwhelmed with the work needed to create the huge number of links to provide full traceability from solution requirements to design for this solution. How can the BA justify omitting all possible links?
A business analyst (BA) is validating requirements and has found that the design cannot be validated to support the requirements. Which of the following is creating this situation?
A senior business analyst (BA) is tasked with verifying a set of requirements written by a junior BA for a
system. During this exercise, the junior BA will ensure that the requirements exhibit atomic characteristics. The senior BA will be verifying that the requirements:
A business analyst (BA) is working on a project that follows incremental and iterative approaches. The BA and the stakeholders have shortlisted several user stories to be considered in the project scope. Which of the following methods would enable them to arrive at a common understanding on delivering value in the product and ranking the stories?
A business analyst (BA) was asked by the vice president (VP) to evaluate the organization's claims processing capability and recommend improvements. The VP agreed to the BA's recommended solution approach and identified an external vendor to develop the modernized claims processing system. Before contracting with the external vendor, the BA realized that the budget should be approved by the Chief Financial Officer. What was missed by the BA when performing stakeholder analysis?
A business analyst (BA) is working on a project involving the purchase of a commercial off-the-shelf (COTS) product. All internal risks have been identified and assessed. What is the BA's next course of action?
You are the business analyst for your organization and you're creating a business analysis communication management plan. In your plan, you want to address the different locales and culture and the communication needs that may affect the business analysis approach. Which one of the following elements should not be included in the cultural analysis of the plan?
A business analyst (BA) has completed an impact analysis of a proposed change, gained approval for the change, and has updated the requirements. The project sponsor wants to be updated with an overview of the results. How should the BA communicate the results?
A business analyst (BA) is structuring requirements to ensure they are cohesive and tell the full story. Which of the following requirements is consistent with a stakeholder's need: “As a Product Manager, I want to review my general insurance sales performance so I track my sales performance against my annual target”?
A business analyst (BA) has elicited requirements for a new system. A subset of these requirements refers to judging the performance of the system, such as efficiency, capacity, security, and scalability. What technique is used to examine and group these requirements?
Two business analysts (BAs) are working on a requirement elicitation activity. One BA comes across a checklist that contains stakeholder details such as who are involved, location, group dynamics that are to be considered before beginning the elicitation activity and seeks a clarification from the second BA. The other BA explains that these details, along with several other items mentioned in the checklist, are required to:
A system owner calls the project team to inquire about a recent change in one of the requirements, and insists that the change was never requested. What should the project team do to investigate the issue?
A business analyst (BA) has decided to use a passive/unnoticeable job shadowing elicitation approach. What is an advantage of using this technique?
Performance measures have been collected and analyzed by a business analyst (BA) to evaluate a solution that was launched a few years ago; however, the performance measures do not indicate whether or not the solution is contributing to the desired value. What is the recommended next step?
A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA do to ensure maximum benefit for the stakeholders?
The business analyst (BA) recommended a new application be rolled out in phases. After reviewing alternatives, the project sponsor agreed. What does the BA expect to achieve by this approach?
A business analyst (BA) is currently verifying the accuracy and consistency of information obtained from the stakeholders. The BA needs to identify additional information. What should the BA do next?
The business analysis (BA) team is evaluating a new commercial off-the-shelf (COTS) application that will be implemented in the coming months. The company has over 20 legacy systems deployed. The Chief Information Officer (CIO) is worried about the need for integration and that some key linkages are missing.
What is the BA team evaluating?
A business analyst (BA) must model information characteristics across multiple information systems for a project. What type of model captures this information?
A large online retailer is introducing new technology to upgrade its aging ordering process. The business analyst (BA) has drawn a stakeholder matrix showing information on how to engage with the stakeholders throughout the project.
Using the stakeholder matrix as a guide, how should the BA engage the suppliers?
The business analyst (BA) has scheduled an informal review of audit requirements with the compliance officer. The BA wants to demonstrate that the requirements collectively support one another so begins with reviewing the:
A business analyst (BA) is conducting a workshop with the purpose of analyzing a business process. Stakeholders of different business units are in attendance. Each stakeholder is able to explain their unit's contribution to the process, however, there is no end to end process owner who can provide a consolidated view. Which technique should the BA use to compare the stakeholder's inputs against each other in order to check for consistency and omissions?
A business analyst (BA) has been spending the majority of the past week cataloguing the new, removed, and modified components of an upcoming project. What is the main purpose of the BA performing this work?
Stakeholders need a financial report that can be published and distributed to multiple end users. They would also like the report to be developed within a specific time frame and within cost. What must the business analyst (BA) do to achieve this goal?
The business analyst (BA) assigned to support a legacy system has developed a customer survey to assess its usability. Before distributing the survey, what should the BA do?
A business analyst (BA) working with a large insurance corporation interviewed an industry thought leader who predicted that many of the regulations currently imposed by the government will change very soon. The BA carefully documented all these inputs from the thought leader because it will impact many of the strategic initiatives of the insurance company. What specific element of requirement validation is being executed by the BA?
A business analyst (BA) is informing stakeholders about the importance of quality when eliciting requirements. What characteristic describes a quality requirement?
A team of business analysts (BAs) identified policies that dictate how the organization grants paid time off for its employees and the associated business rules. What is this team of BAs trying to do?
A business analyst (BA) needs to make sure that the business analysis information is securely stored and accessible to stakeholders. Which element helps in achieving that goal?
When a business analyst performs requirements tracing, he may need to trace the requirements backward through their lineage and may need to trace the requirements forward through their relationship to other requirements. What is the forward tracing activity called in requirements traceability?
In order to have high quality in requirements, all of the following characteristics should exist in the requirements except for which one?
What do business goals and objectives of enterprise analysis actually describe?
You are the business analyst for your organization. On your current project you'll be using the change-driven approach for defining requirements and gathering feedback. Which of the following statements best describes the change-driven approach?
You are a business analyst in an organization that has recently embraced business analysis as part of its initiative for new projects. In this organization, there is not an organizational standard for tailoring business analysis duties and expectations. Which one of the following best describes the action you should take to begin business analysis?
If a requirement has been satisfied, why is it still considered a requirement?
You are the business analyst for your organization and you're working with your team to define the business problem. As part of this analysis, you've identified the adverse impacts of the problem, the benefits from a
potential solution, and how quickly the problem could be solved. What other element should you consider?
Bonny is the business analyst for her organization and she's making a determination from which vendor the solution should be purchased. She has identified several categories to measure each vendor's overall performance and solution. cost, schedule, experience, certification, references, and years in business. For each category, she has identified scores the vendor may earn; for example, cost is worth 25 points, schedule is worth up to 20 points, and years in business is worth up to ten points. The vendor who gets the most points in the assessment will win the contract. What is Bonny using in this scenario?
You are the business analyst in your organization and you're working to organize the requirements for the business units in your company. Which technique is best suited for structuring requirements around the needs of each stakeholder group?
You are the business analyst for your organization and your manager has asked you to prepare an analysis of each proposed solution. Your manager wants you to determine whether and how each option can provide an expected business benefit to meet the stated business need. What is your manager asking you to create?
A business analyst in her organization has identified all of the terminology of the solution, the acronyms the organization will use, and the nomenclature of her department where the endeavor will take place. Where should all of this information actually be stored?
A business analyst (BA) held a formal walk through of requirements developed on a project. Stakeholders expressed concerns because they had different interpretations of the requirements. What activity would help ensure a common understanding?
The following chart represents attendance of subject matter experts (SME) and the solution owner for a requirements review and approval meeting held weekly by a business analyst (BA).
The requirements package was approved by the solution owner during the May 30 meeting. After implementation of the solution, the BA learns that the users in SME-3 s area are not using the system. Which business analysis activity should the BA have monitored more closely to mitigate this situation?
A Chief Information Officer (CIO) was discussing a solution approach for a technology project in a meeting where a business analyst (BA) was also present. Stakeholders were discussing advantages and disadvantages of each solution approach. What should be the top priority for the BA in assessing the solution approach?
A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and resolve the outstanding issues?
A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort. How should the business analyst (BA) handle the situation?
The business analyst (BA) is preparing for requirements review with a group of stakeholders. The BA must determine how best to model the requirements for the review. Which of the following guidelines and tools will the BA use?
The business analyst (BA) has structured information so it is easy to find, does not conflict with other information, and is not duplicated unnecessarily. Which additional factor does the BA need to take into account when deciding how to structure the information?
A business analyst (BA) is working on a project to improve product delivery. The issues arise during the latter stages of the delivery Freecycle and are due to poor communication of the business analysis information from the elicitation phase. As a result, a BA has ensured that the testing and training teams are identified as stakeholders on the RACI Matrix going forward. To which RAG designation should the training and testing teams be added?
A business analyst (BA) is working on a data-centric IT project. The business stakeholders develop the content but do not understand the technical aspects while the IT team believes that there is no need to understand the business issues. Which deliverable will facilitate understanding between IT and the business stakeholders?
System designers are working with a business analyst (BA) during the initial stages of a project to implement a new transaction-based system. The system designers would like to have a visual that illustrates the type of information that will be input in the system, the processes it will support, and the location where it will be stored. What type of diagram meets the designers' needs?
A general insurance company wants to enter a new segment that has the potential for high profit and little competition. The business analyst (BA) was asked to prepare a presentation for key stakeholders to show how the new segment will deliver value for stakeholders. Which of the following is best suited for this purpose?
A company has bought a customizable software product and the vendor's business analyst (BA) is visiting the company's office to perform a requirements assessment. The business sponsor expresses an interest in improving a specific process that is in scope. What should the BA do?
A software development company has a strict policy of evaluating solutions against the number of defects reported in the testing phase. This practice helps the company stay competitive and deliver better solutions. What performance measure is being practiced?
A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?
An organization is experiencing long contracting life cycles when establishing annual contracts with its customers. Upon initial investigation, the outdated application was thought to be the cause, however based on further analysis the business process is found to be flawed. The business analyst (BA) wants to model the people involved in the process. Which of the following techniques models the responsibilities of these stakeholders?
A business analyst (BA) elicits requirements from end users for a new application, and then completes a set of use cases and use case scenarios. What should the BA do next?
A business analyst (BA) has recently joined a large consultancy firm where BAs are globally distributed on different assignments. Where would the BA find expectations for business analysis work as mandated by the consultancy firm?
A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications which are not being updated. What is the first thing that a business analyst (BA) should consider?
A senior business analyst (BA) must review the requirements specification of a junior BA. The senior BA puts together a list of key evaluation criteria to guide the determination of a requirement's quality. Which of the criteria below is a characteristic of a quality requirement?
A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture the information in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?
A business analyst (BA) is defining relationships between business requirements and solution components. Which guideline will the BA use to accomplish this?
A newly implemented personal loan financing system has been in operation for one month. The business objective is to reduce the loan processing time from 11 days to 3 days but it is currently occurring in 4.5 days. What must the business analyst (BA) do next?
A business analyst (BA) is assigned a new project and is beginning to prepare for elicitation. Which task must the BA complete before preparation of the elicitation process can begin?
A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company's risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors. What is the company's attitude toward risk, as assessed by the BA?
A business analyst (BA) has completed multiple workshops involving a number of stakeholders including the project manager however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?
After an initial project kick-off meeting, the business analyst (BA) determined that the project has a short deadline and a regulatory mandate with stiff penalties for non-compliance. The stakeholders do not want to risk missing the deadline, and management is willing to commit any amount of resources to meet the deadline. Which kind of approach is suitable for the initiative?
Which tool will allow a business analyst (BA) to determine how information is input, processed, stored, and extracted from a collection of systems?
Two stakeholders are arguing over which model to use for describing requirements. One insists that using an activity diagram is superior while the other prefers a state diagram. How should the business analyst (BA) resolve the conflict?
During a senior management meeting about a project at the requirements analysis stage, a business analyst (BA) stated that there were a number of workarounds associated with the current application. The Chief Information Officer (CIO) was looking for ways to improve the situation and the BA suggests a solution. Which of the following can the BA suggest that the organization consider to increase efficiencies?
An organization has identified a market opportunity that could result in significant business gains. A business analyst (BA) is asked to assist in building the new business model. The BA begins by analyzing the current state. What input is critical to the current state analysis?
A recent survey shows that a newly implemented system has features that the users have never used. Upon reviewing the survey report, the Chief Executive Officer (CEO) highlighted that the company must avoid future implementations with functionality that does not provide any business value. What must the business analyst (BA) do to ensure future requirements meet a business need?
A business analyst (BA) is working on a project for a media company. The BA has verified, validated, and prioritized the requirements based on business benefits. During the development phase, the team discovered that the current viewer will no longer be supported by the provider. The technical team needs to either upgrade to the newer version with different technology or find an alternate viewer. Given this new information, what is the next step for the BA?
The business analyst (BA) is helping the business stakeholders prioritize requirements for a new customer portal for managing orders, delivery, and payment information. A number of requirements address compliance with regulations regarding access for people with disabilities. What factor should the BA use to guide the stakeholders when assigning a priority for these specific requirements?
A business analyst (BA) is working on a project that has a number of stakeholder conflicts and issues. The BA is finding it difficult to resolve the conflicts and issues effectively. What should the BA do to prevent a similar situation in the future?
A project manager asks a business analyst (BA) to conduct a meeting to walk the stakeholders through how requirements are structured. Which of the following requirement viewpoints will help the BA provide that information?
A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities. Which element of stakeholder management is the BA performing?
As part of a strategic initiative, a bank decides to expand operations to a new country where the most commonly used language is Spanish. The bank's current mobile application only supports English. The organization initiates a project to provide local language support for the app. From which level did the business need originate?
A project manager (PM) is planning the project timelines along with a business analyst (BA) and they come across the task of requirement allocation. The PM wants to know what the dependencies are before the requirement allocation task is initiated and seeks the BA's advice. Which of the following is a dependency that the BA will highlight as a predecessor for requirement allocation?
A business analyst (BA) is preparing for elicitation activities and needs to determine who should be consulted, who should participate, and what roles each should fill. Which elicitation technique should the BA use?
Certification of Capability in Business Analysis | CCBA Questions Answers | CCBA Test Prep | Certification of Capability in Business Analysis (CCBA) Questions PDF | CCBA Online Exam | CCBA Practice Test | CCBA PDF | CCBA Test Questions | CCBA Study Material | CCBA Exam Preparation | CCBA Valid Dumps | CCBA Real Questions | Certification of Capability in Business Analysis CCBA Exam Questions