What are the key features of using a low level code? Note: There are 2 correct answers to this question.
For a production version to be valid consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.
Why do you use Engineering Change Management? Note: There are 2 correct answers to this question.
What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
What are the prerequisites for a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.
Your company produces a finished good based on a forecast expects it to be in stock when customers order it. If customers order more than the forecasted quantity this must NOT have any impact on the production program.
Which planning strategy do you use?
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.
How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.
Which of the following are features of the clean core dashboard? Note: There are 2 correct answers to this question.
What are some SAP recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.
Which business processes are affected by settings in the order type dependent parameters? Note: There are 2 correct answers to this question.
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.