Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Questions 4

What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling of an operation takes place as close as possible to the desired date.

B.

Sequencing on multi-activity resources is automatically updated.

C.

Neighboring operations can be moved in both directions in order to create a slot.

D.

Changes are automatically implemented in the complete collective order.

Buy Now
Questions 5

Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Production cost collector

B.

Production version

C.

Repetitive manufacturing profile

D.

Routing

Buy Now
Questions 6

You use planning strategy Finite Scheduling with Reverse and want to allow scheduling in the past. How can you parameterize this in the strategy profile?

Options:

A.

Specify a negative offset time.

B.

Specify a negative opening period.

C.

Specify a negative planning horizon.

D.

Specify a negative PP/DS horizon.

Buy Now
Questions 7

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.

Options:

A.

Queue time

B.

Teardown time

C.

Move time

D.

Setup time

Buy Now
Questions 8

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

Options:

A.

Wait time

B.

Float before production

C.

Processing time

D.

Pick time

E.

Setup time

Buy Now
Questions 9

Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.

Options:

A.

Resource hierarchy

B.

Resource selection

C.

Resource matrix

D.

Resource network

Buy Now
Questions 10

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

Options:

A.

Assign the alert profile to the overall profile.

B.

Assign the overall profile to the authorization profile.

C.

Create an object selection variant for alerts according to the priority of ATP categories.

D.

Create an object selection variant for production-planning-related alerts.

Buy Now
Questions 11

What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

Options:

A.

Order type

B.

Requirements profile

C.

Requirements type

D.

Planning strategy

Buy Now
Questions 12

Where does the system check master data selection settings during the creation of planned orders or production orders? Note: There are 3 correct answers to this question.

Options:

A.

In the production version

B.

In the work centers

C.

In the bill of material (BOM)

D.

In the MRP controller

E.

In the routing

Buy Now
Questions 13

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?

Options:

A.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

B.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

C.

The new operation is inserted at the desired time; the previously dispatched operation is moved forward.

D.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward.

Buy Now
Questions 14

Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a resource group.

B.

Use a planning group.

C.

Use a propagation range.

D.

Use a planning area.

Buy Now
Questions 15

How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.

Options:

A.

Digital signature

B.

Approved resources

C.

Recipe approval

D.

GMP-compliant flag

E.

Batch record

Buy Now
Questions 16

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

First in first out (FIFO)

B.

Simultaneous

C.

Manual maintenance

D.

100% check

Buy Now
Questions 17

What are some benefits of planning with planned independent requirements for finished materials? Note: There are 2 correct answers to this question.

Options:

A.

Reduced delivery times

B.

Reduced times for final assembly

C.

Option to forecast planning for production resources

D.

Option to use make-to-order production

Buy Now
Questions 18

What options does a planner have in the planning table for repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Change the assignments of production quantities to production lines.

B.

Create new production quantities.

C.

Dispatch operations to work centers.

D.

Reschedule and deallocate operations.

Buy Now
Questions 19

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

Options:

A.

Opening period

B.

Total replenishment lead time

C.

Float after production

D.

Setup time

Buy Now
Questions 20

In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Options:

A.

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

B.

MRP creates the capacity requirements without considering existing load on the work centers.

C.

MRP creates the capacity requirements at the earliest possible time.

D.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Buy Now
Questions 21

What is the difference between co-products and by-products? Note: There are 2 correct answers to this question.

Options:

A.

Only co-products have a non-zero inventory valuation.

B.

Only co-products have movement type 531.

C.

Only co-products have movement type 101.

D.

Only co-products appear in the process or production order settlement rule.

Buy Now
Questions 22

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.

Options:

A.

Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

B.

Add the agreement to the source list mark it for MRP relevance.

C.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

D.

Add the agreement to the quota arrangement mark it for MRP relevance.

Buy Now
Questions 23

Which information is required when you create a product master in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

Base unit of measure

B.

Industry sector

C.

Selection screen for views

D.

Product type

Buy Now
Questions 24

Which standard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Variable-size item

B.

Work item

C.

Preliminary item

D.

WBS item

Buy Now
Exam Code: C_TS422_2023
Exam Name: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Last Update: Apr 21, 2025
Questions: 80
C_TS422_2023 pdf

C_TS422_2023 PDF

$29.75  $84.99
C_TS422_2023 Engine

C_TS422_2023 Testing Engine

$35  $99.99
C_TS422_2023 PDF + Engine

C_TS422_2023 PDF + Testing Engine

$47.25  $134.99