How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,
You can you use capacity availability checks for production orders, which settings have to be made for this?
Note: There are 2 Correct answers to this question?
You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?
How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.
Which time elements are relevant for lead time scheduling of a production order? Note:
There are 2 correct answers to this question.
which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
What does the material type influence?
Note: There are 2 correct answers to this question.
Which master data fields can have an impact on whether MRP creates planned orders or purchase
requisitions for a material?
Note: There are 2 Correct answers to this question?
in your Plant, MRP is activated.
which options do you have to exclude a material from the MRP run?
Note: there are 2 correct answers to this question.
Which master data object governs the relationship between supply source and demand source in the Kanban process?
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable and physically connected tanks? Note: There are 2 correct answers to this question.
How can you support a GMP (Good Manufacturing Practice)-compliant production process?
Note: There are 3 correct answers to this question.
Which of the following elements does MRP take into account during net requirement
calculation? Note:
There are 2 correct answers to this question.
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.
which actions does the system perform by default when you save a confirmation for a finished
product in repetitive manufacturing?
Note: There are 3 Correct answers to this question.
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?
Note: There are 2 correct answers to this question.
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?
Note: There are 2 correct answers to this question