Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Questions 4

How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,

Options:

A.

By Plant

B.

By Period

C.

By Industry

D.

By Material Status

Buy Now
Questions 5

You can you use capacity availability checks for production orders, which settings have to be made for this?

Note: There are 2 Correct answers to this question?

Options:

A.

The relevant for finite scheduling indicator must be set.

B.

A checking rule must be assigned to the work centers

C.

An overall profile must be assigned in the checking control

D.

The scope of check must be defined in customizing.

Buy Now
Questions 6

You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?

Options:

A.

Manual Planning Without Check

B.

Consumption-Based Planning

C.

Material Requirements Planning

D.

Advanced Planning

Buy Now
Questions 7

How can a material availability check be triggered automatically for a production order?

Note: There are 2 correct answers to this question.

Options:

A.

By capacity planning

B.

By mass processing

C.

By order release

D.

By order confirmation

Buy Now
Questions 8

Which time elements are relevant for lead time scheduling of a production order? Note:

There are 2 correct answers to this question.

Options:

A.

setup time

B.

Opening Period

C.

Float after Production

D.

Total replenishment lead time

Buy Now
Questions 9

which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?

Options:

A.

you can use mass processing to set production orders to technically complete

B.

you can use the production scheduling profile to automatically set orders toI technicallycomplete

C.

You can use trigger points to automatically create rework orders via confirmation.

D.

You can use mass processing to read PP master data for production orders

Buy Now
Questions 10

What is the work center hierarchy in capacity planning?

Options:

A.

A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of alternative work centers for production, structured in hierarchy levels by priorities

Buy Now
Questions 11

Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

Options:

A.

The same batch management level is used

B.

The same base unit of measure is used.

C.

The quantity and value updates are the same

D.

The same account category is used

Buy Now
Questions 12

What does the material type influence?

Note: There are 2 correct answers to this question.

Options:

A.

Which document types and class categories are allowed

B.

Which material master screens appear and in which sequence

C.

Whether the material is produced in-house, procured externally, or both

D.

Which plant-specific and plant-independent statuses are allowed

Buy Now
Questions 13

Which master data fields can have an impact on whether MRP creates planned orders or purchase

requisitions for a material?

Note: There are 2 Correct answers to this question?

Options:

A.

MRP Groups

B.

Material Type

C.

MRP type

D.

Procurement Type

Buy Now
Questions 14

in your Plant, MRP is activated.

which options do you have to exclude a material from the MRP run?

Note: there are 2 correct answers to this question.

Options:

A.

Use a specific material status

B.

Use a specific material group

C.

Use a specific MRP type

D.

Use a specific MRP list

Buy Now
Questions 15

Which master data object governs the relationship between supply source and demand source in the Kanban process?

Options:

A.

Replenishment strategy

B.

Production supply area

C.

Control cycle

D.

Rate routing

Buy Now
Questions 16

Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable and physically connected tanks? Note: There are 2 correct answers to this question.

Options:

A.

Resource matrix

B.

Resource network

C.

Resource hierarchy

D.

Resource selection

Buy Now
Questions 17

How can you support a GMP (Good Manufacturing Practice)-compliant production process?

Note: There are 3 correct answers to this question.

Options:

A.

Approved resources

B.

Digital signature

C.

Batch record

D.

GMP-compliant flag

E.

Recipe approval

Buy Now
Questions 18

Which of the following elements does MRP take into account during net requirement

calculation? Note:

There are 2 correct answers to this question.

Options:

A.

Forecast key figures

B.

Safety Stock

C.

Maximum stock level

D.

Purchase orders

Buy Now
Questions 19

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.

Options:

A.

Increase the capacity supply in a time-phased interval.

B.

Determine a time period with available capacity on the planning board.

C.

Execute an infinite production planning run for the critical resources.

D.

Reduce the planning Window.

E.

Form optimum sequence to reduce setup times.

Buy Now
Questions 20

which actions does the system perform by default when you save a confirmation for a finished

product in repetitive manufacturing?

Note: There are 3 Correct answers to this question.

Options:

A.

Posting of production costs to the production cost collector

B.

posting of goods receipt for the product

C.

Reduction of associated capacity requirements

D.

Archiving of document for assembly scrap

E.

Material staging for next order in sequence

Buy Now
Questions 21

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling agreement schedule line

B.

Purchase Order

C.

Planned Order

D.

Production Order

Buy Now
Questions 22

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Work center capacities chart

D.

Orders (dispatched) chart

Buy Now
Questions 23

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?

Note: There are 2 correct answers to this question

Options:

A.

Total replenishment lead time

B.

Operation duration

C.

Planned delivery time

D.

In-house production time

Buy Now
Questions 24

What can you use heuristics in Advanced Planning (PP/DS) for?

Options:

A.

To optimize costs and times in production plans

B.

To solve planning problems for defined objects

C.

To automate material movements in material staging

D.

To set default values in production master data

Buy Now
Exam Code: C_TS422_2023
Exam Name: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Last Update: Sep 15, 2024
Questions: 80
C_TS422_2023 pdf

C_TS422_2023 PDF

$28  $80
C_TS422_2023 Engine

C_TS422_2023 Testing Engine

$33.25  $95
C_TS422_2023 PDF + Engine

C_TS422_2023 PDF + Testing Engine

$45.5  $130