Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

APM-001 Associate in Project Management (APM) Questions and Answers

Questions 4

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Buy Now
Questions 5

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

Options:

A.

To the project management plan.

B.

To the risk register.

C.

In the scope verification processes.

D.

And their impact to the project in terms of time, cost, and risk.

Buy Now
Questions 6

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

Options:

A.

Control charts

B.

Pareto diagrams

C.

Ishikavva diagrams

D.

Checksheets

Buy Now
Questions 7

An input to the Create WBS process is a:

Options:

A.

project charter.

B.

stakeholder register.

C.

project scope statement.

D.

requirements traceability matrix.

Buy Now
Questions 8

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Buy Now
Questions 9

Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Buy Now
Questions 10

What are the Project Procurement Management processes?

Options:

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Buy Now
Questions 11

Prototype development may be used as a tool for which of the following risk response strategies?

Options:

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Buy Now
Questions 12

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Buy Now
Questions 13

Administer Procurements is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Buy Now
Questions 14

Resource calendars are included in the:

Options:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Buy Now
Questions 15

Risk exists the moment that a project is:

Options:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

Buy Now
Questions 16

The correct equation for schedule variance (SV) is earned value:

Options:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Buy Now
Questions 17

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

Options:

A.

Portfolio

B.

Project

C.

Program

D.

Operations

Buy Now
Questions 18

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Buy Now
Questions 19

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Buy Now
Questions 20

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Options:

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Buy Now
Questions 21

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Questions 22

To which process is work performance information an input?

Options:

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 23

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Buy Now
Questions 24

An input to the Plan Cost Management process is:

Options:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Buy Now
Questions 25

An output of the Plan Quality Management process is:

Options:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Buy Now
Questions 26

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Buy Now
Questions 27

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Buy Now
Questions 28

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Buy Now
Questions 29

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Buy Now
Questions 30

An input to the Control Quality process is:

Options:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Buy Now
Questions 31

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Buy Now
Questions 32

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

Options:

A.

Responses

B.

Appetite

C.

Tolerance

D.

Attitude

Buy Now
Questions 33

Which item is an example of personnel assessment?

Options:

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Buy Now
Questions 34

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Questions 35

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Options:

A.

Feedback analysis

B.

Stakeholder analysis

C.

Communication management plan

D.

Stakeholder management plan

Buy Now
Questions 36

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

Options:

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Buy Now
Questions 37

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Buy Now
Questions 38

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Buy Now
Questions 39

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Buy Now
Questions 40

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Buy Now
Questions 41

Which process requires implementation of approved changes?

Options:

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Buy Now
Questions 42

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Buy Now
Questions 43

Inputs to the Plan Schedule Management process include:

Options:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

Buy Now
Questions 44

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (T&M)

Buy Now
Questions 45

A regression line is used to estimate:

Options:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Buy Now
Questions 46

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Options:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Buy Now
Questions 47

Assigned risk ratings are based upon:

Options:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders' tolerances.

Buy Now
Questions 48

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOKĀ® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Buy Now
Questions 49

A project manager builds consensus and overcomes obstacles by employing which communication technique?

Options:

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Buy Now
Questions 50

In which Knowledge Area is the project charter developed?

Options:

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Buy Now
Questions 51

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

Options:

A.

Develop Project Team.

B.

Manage Project Team.

C.

Acquire Project Team.

D.

Plan Human Resource Management.

Buy Now
Questions 52

The number of potential communication channels for a project with 5 stakeholders is:

Options:

A.

10.

B.

12.

C.

20.

D.

24.

Buy Now
Questions 53

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 54

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Buy Now
Questions 55

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Buy Now
Questions 56

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Buy Now
Questions 57

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

17

Buy Now
Questions 58

Which tool or technique is required in order to determine the project budget?

Options:

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

Buy Now
Questions 59

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Buy Now
Questions 60

When closing a project or phase, part of the process may require the use of which type of analysis?

Options:

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Buy Now
Questions 61

Which items are components of a project management plan?

Options:

A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Buy Now
Questions 62

Every project creates a unique product, service, or result that may be:

Options:

A.

tangible

B.

targeted

C.

organized

D.

variable

Buy Now
Questions 63

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

Options:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Buy Now
Questions 64

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Buy Now
Questions 65

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Buy Now
Questions 66

At the start of a typical project life cycle, costs are:

Options:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Buy Now
Questions 67

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

Options:

A.

0.8

B.

1

C.

1.25

D.

1.8

Buy Now
Questions 68

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Buy Now
Questions 69

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 70

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

Options:

A.

Technical approach

B.

Technical capability

C.

Business size and type

D.

Production capacity and interest

Buy Now
Questions 71

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Buy Now
Questions 72

Which defines the portion of work included in a contract for items being purchased or acquired?

Options:

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Buy Now
Questions 73

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Buy Now
Questions 74

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Buy Now
Questions 75

Which type of managers do composite organizations involve?

Options:

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Buy Now
Questions 76

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

Options:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

Buy Now
Questions 77

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Buy Now
Questions 78

Which is an example of Administer Procurements?

Options:

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Buy Now
Questions 79

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 80

An input required in Define Scope is an organizational:

Options:

A.

structure.

B.

process asset.

C.

matrix.

D.

breakdown structure.

Buy Now
Questions 81

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Buy Now
Questions 82

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

Options:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Buy Now
Questions 83

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

Options:

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

Buy Now
Questions 84

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T&M).

Buy Now
Questions 85

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Project document updates

B.

Organizational process assets updates

C.

Change requests

D.

Deliverables

Buy Now
Questions 86

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited

B.

Low to moderate

C.

Moderate to high

D.

High to almost total

Buy Now
Questions 87

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Buy Now
Questions 88

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

Options:

A.

stakeholder management strategy.

B.

communications management plan,

C.

stakeholder register,

D.

performance report.

Buy Now
Questions 89

What is a tool to improve team performance?

Options:

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Buy Now
Questions 90

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Buy Now
Questions 91

Which Process Group contains those processes performed to define a new project?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Buy Now
Questions 92

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

Options:

A.

There is a cost underrun.

B.

There is a cost overrun.

C.

The project may not meet the deadline.

D.

The project is 20 days behind schedule.

Buy Now
Questions 93

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

Options:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Buy Now
Questions 94

Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

Options:

A.

Cause and effect diagram

B.

Control charts

C.

Pareto chart

D.

Histogram

Buy Now
Questions 95

In a weak matrix, the project managers role is:

Options:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Buy Now
Questions 96

In which domain of project management would a Pareto chart provide useful information?

Options:

A.

Project Scope Management

B.

Project Time Management

C.

Project Communications Management

D.

Project Quality Management

Buy Now
Questions 97

"Tailoring" is defined as the:

Options:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

B.

act of creating a project team with the specialized skills required to produce a required product or service.

C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Buy Now
Questions 98

In which Process Group are lessons learned documented?

Options:

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Buy Now
Questions 99

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Buy Now
Questions 100

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Buy Now
Questions 101

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Buy Now
Questions 102

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

Options:

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Buy Now
Questions 103

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Buy Now
Questions 104

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

Options:

A.

Three weeks

B.

Four weeks

C.

Five weeks

D.

Six weeks

Buy Now
Questions 105

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Buy Now
Exam Code: APM-001
Exam Name: Associate in Project Management (APM)
Last Update: Nov 21, 2024
Questions: 0
APM-001 pdf

APM-001 PDF

$28  $80
APM-001 Engine

APM-001 Testing Engine

$33.25  $95
APM-001 PDF + Engine

APM-001 PDF + Testing Engine

$297.5  $850