New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

RCDDv14 BICSI Registered Communications Distribution Designer – RCDDv14 Questions and Answers

Questions 4

During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and

Options:

A.

cost projections.

B OSHA specifications

B.

client requirements

C.

equipment availability

Buy Now
Questions 5

Program manager B leaves the program and program manager A takes over the program responsibilities Program manager A wants to ensure that all expected benefits of the program are realized.

What is used to assess the program cost/benefit justification?

Options:

A.

Program charter

B.

Benefits management plan

C.

Program business case

D.

Program scope statement

Buy Now
Questions 6

What should a program manager do to ensure that the program meets the organization's strategic goals?

Options:

A.

Manage the program delivery phase

B.

Analyze the benefits management plan

C.

Assess the program reports

D.

Engage the program steering committee

Buy Now
Questions 7

A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?

Options:

A.

Milestone dates, budget, and staff details that support it

B.

Assumptions incorporated into the benefits management plan

C.

Process within the organization that will be needed to deliver the product

D.

Key decision makers or stakeholders in the program and their expectations and interests

Buy Now
Questions 8

A new program is comprised of four component projects. The program manager must assign project managers to each of the tour projects. There are eight potential project managers to consider. What should the program manager do before assigning the project managers?

Options:

A.

Determine budgetary constraints related to the project managers' salaries

B.

Request performance feedback from the project managers' line managers

C.

Evaluate the project managers' skills and match them to the needs of the projects

D.

Interview each project manager to determine their career aspirations

Buy Now
Questions 9

The program manager of a multinational program must reconcile data including subject matter experts* labor hour estimates and other direct resource hour estimates. In addition the program manager must prepare the cash flow analysis

Which of the following should be considered to get a baseline budget?

Options:

A.

Currency exchange rates

B.

Component cost estimates

C.

Baseline schedule

D.

Program payment schedules

Buy Now
Questions 10

A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's headquarters Five regional sales departments are located at different locations around the world.

At this stage of the program, what is the first step?

Options:

A.

Develop a program work breakdown structure

B.

Identify and quantify business benefits of the program

C.

Determine and prioritize the various components of the program

D.

Prepare a program organization chart covering both sales and production

Buy Now
Questions 11

A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?

Options:

A.

Assign project A's resource to project B

B.

Reassign the resource to project B after protect A ends

C.

Prioritize the resource to optimize their use across both projects A and B

D.

Mitigate risk by leveraging other resources in project A

Buy Now
Questions 12

The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization

What should the program manager do next?

Options:

A.

Update the program benefits management plan and risk register

B.

Implement the mitigation plan for the identified risk

C.

Adjust the program scope to avoid the risk

D.

Document the risk and create a mitigation plan

Buy Now
Questions 13

Alter an organization initiates a strategic program several project managers express interest in joining the program Team. The program manager's supervisor recommends a list of project managers to be part of the team

What should the program manager do to select the project managers''

Options:

A.

Complete a skill set inventory and select the most suitable resource(s)

B.

Ask interested project managers for their CV or resume and conduct Interviews

C.

Accept the recommendation of the program manager's supervisor

D.

Contact the human resource manager tor project managers' availability

Buy Now
Questions 14

A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?

Options:

A.

Program sponsor

B.

Communications manager

C.

Project manager

D.

Program manager

Buy Now
Questions 15

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program

As a result, the program manager must do which of the following'?

Options:

A.

Utilize team members that are currently available, even though they do not have the expertise needed.

B.

Assign the tasks on the critical path to the resources available to adhere to the project schedule

C.

Delay the start of the program until the assigned resources are available

D.

Apply resource leveling considering the constraints of time, budget, and quality

Buy Now
Questions 16

The marketing department of a firm has tasked the organization to design a structured cabling system allowing them to support either 10G6aseT or HDBASE-T. The budget requires that only one cable type be installed and that it be MINIMUM compliant. Of the following choices, what is the choice with the MINIMUM solution/solutions for the client?

Options:

A.

Category 5e

B.

Category 6

C.

Category 6A

D.

Category 7

Buy Now
Questions 17

What would prevent a program manager from completing program closure once a program has been completed?

Options:

A.

Failure to update the financial management plan

B.

Failure to update the benefits register

C.

Incomplete realization of all program benefits

D.

Failure to obtain program steering committee approval

Buy Now
Questions 18

Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance

To resolve this situation, which of the following must go through critical review and change"?

Options:

A.

Program Benefits Management domain

B.

Stakeholder communications requirements

C.

Program communications report

D.

Program communications management plan

Buy Now
Questions 19

Which service is NOT typical of Grade 1?

Options:

A.

Telephone

B.

Multimedia

C.

Data

D.

Television

Buy Now
Questions 20

When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

Options:

A.

Taxes

B.

Permits

C.

Inspection

D.

Licensing

E.

Safety

Buy Now
Questions 21

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk

What should the program manager do to monitor and control the supplier?

Options:

A.

Use expert judgment and update the program procurement plan

B.

Seek stakeholder approval of program procurement management activities

C.

Examine performance reports, audits, and inspections

D.

Review proposal evaluation criteria, risk analyses, and mitigation strategies

Buy Now
Questions 22

For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a

Options:

A.

SoW.

B.

spare ad sheet

C.

worksheet

D.

database

Buy Now
Questions 23

A program delivers incremental benefits but is far from closure. The company completes an acquisition and defines new strategic objectives.

What should the program manager do next?

Options:

A.

Evaluate the impact of the new strategic objectives through a change request

B.

Integrate the new acquisition into the program to include the new strategic objectives

C.

Assess the impact of the new acquisition on the contract management plan

D.

Review the benefits management plan to assess the continued validity of the program

Buy Now
Questions 24

An ICT distribution designer is reviewing a client's site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a___________design process

Options:

A.

logical network

B.

top-down

C.

bottom-up

D.

functional

Buy Now
Questions 25

Which of the following two items are examples of items associated with a submittal? (Select two options.)

Options:

A.

Request tor permits

B.

As-built

C.

Shop Drawings

D.

Product Data

E.

Punch List

Buy Now
Questions 26

A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement

What should the program manager do first?

Options:

A.

Meet with the program management office to update the benefits management plan

B.

Meet with the organization's strategic planning committee to obtain clarification

C.

Meet with the program sponsor to address the issue

D.

Meet with the customer to determine if the stakeholder's requirement is valid

Buy Now
Questions 27

The program selection committee presents several programs for approval:

Which program was selected based solely on a three-year return on investment?

Options:

A.

Program A

B.

Program B

C.

Program C

D.

Program D

Buy Now
Questions 28

A sponsor decides that the business environment is unfavorable for continuation of a program.

The sponsor asks that the program be closed.

What items should be completed as part of the program's final report?

Options:

A.

Lessons learned, successes and failures, and financial and performance assessments

B.

Final updates to the benefits register, successes and failures, and resource disposition

C.

Financial and performance assessments, successes and failures, and reason(s) for program closure

D.

Knowledge transition, successes and failures, and reason(s) for program closure

Buy Now
Questions 29

The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system. What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?

Options:

A.

2

B.

4

C.

6

D.

8

Buy Now
Questions 30

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.

Which of the following actions should the program manager take?

Options:

A.

Focus on the internal stakeholders to ensure cost and) schedule objectives are achieved

B.

Balance stakeholder needs through the use of trade-offs among the stakeholder groups

C.

Focus on the external stakeholders to ensure the intended benefits are achieved

D.

Conduct a stakeholder meeting to allow everyone to state their priorities

Buy Now
Questions 31

What actions are taken in the process of developing and maintaining a program risk register?

Options:

A.

Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies and provide the foundation for the risk management plan

B.

Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies and identify the root cause of potential risks

C.

Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and proactively manage program issues

D.

Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify residual risks.

Buy Now
Questions 32

A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete

What should the program manager do to understand the financial environment?

Options:

A.

Map costs to the expected benefits realization

B.

Establish intermediate budget based on historical information

C.

Establish program financial framework

D.

Obtain intermediate funding from the executive sponsor

Buy Now
Questions 33

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

Options:

A.

The component has released resources to meet program objectives

B.

The component has met the quality requirements to meet program objectives

C.

The component has met the schedule requirements to meet program objectives

D.

The component has met the benefits realization criteria to meet program objectives

Buy Now
Questions 34

Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect

Options:

A.

Authority

B.

Having Jurisdiction (AHJ)

C.

Construction Manager

D.

ICT Distribution Designer/Project Manager

Buy Now
Questions 35

A program manager for the construction of an international event venue that will impact the local community needs to determine the best approach for communications. One of the conditions of the program is that after the event takes place a park will be built for the community's use.

What should the program manager do to ensure community support?

Options:

A.

Review the scope with the program sponsor and community representatives

B.

Organize an advocacy group and facilitate community engagement

C.

Negotiate the program scope with community representatives

D.

Ensure community representatives are part of the steering committee

Buy Now
Questions 36

Which of the following options BEST describes Request for Quote (RFQ)?

Options:

A.

Usually provides more detail involved with selecting the material, equipment, and components required during implementation (e.g. make, model, performance specifications)

B.

Can be submitted by the contractor in response to a field order or as an uninitiated request for a change in scope

C.

Used to obtain a formal response to the contract documents

D.

An invitation for the design professionals (e g, architect, engineer, consultant) or contractors to submit a proposal for services

Buy Now
Questions 37

What is the PRIMARY reason for considering a physical ting topology for connecting outlying buildings?

Options:

A.

It is the most cost effective design ten a campus network.

B.

It provides a redundant cable path for disaster recovery.

C.

It is the most compelling design for any network requirement.

D.

It is an easier physical design to install.

Buy Now
Questions 38

What category/class of cabling does BICSI recommend for the MINIMUM performance level of horizontal balanced twisted-pair cabling?

Options:

A.

Category 5e/class D

B.

Category 6/class E

C.

Category SA/class EA

D.

Category 7/class F

Buy Now
Questions 39

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.

What should be done with the identified potential risk?

Options:

A.

Incorporate it into the risk register and perform a thorough analysis

B.

Mitigate the risk before it is incorporated into the risk management plan

C.

Document the risk in the program transition plan and identify it as a potential issue

D.

Document it m the issue log and immediately notify the steering committee

Buy Now
Questions 40

An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors. What is the loss budget for the above fiber link?

Options:

A.

2.95 dB

B.

3.40dB

C.

3.90 dB

D.

4.35 dB

Buy Now
Questions 41

You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%. What size commercial DD (distribution device) is required to accommodate the increase?

Options:

A.

660 mm (26 in)

B.

1015 mm (40 in)

C.

1346 mm (53 in)

D.

1676 mm (66 in)

Buy Now
Questions 42

An initiative involves the development of new technology and leverages existing technologies It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place. In what phase is the nsk management plan created?

Options:

A.

Program definition

B.

Program execution management

C.

Program delivery

D.

Program risk management planning

Buy Now
Questions 43

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff

What should the program manager do to ensure communications on the component projects are consistent?

Options:

A.

Request a more experienced project manager to work on project 6

B.

Create a program communications management plan across all component projects

C.

Direct all projects to use project A's communications management plan as a template

D.

Rework the communications management plans for all projects to be consistent

Buy Now
Exam Code: RCDDv14
Exam Name: BICSI Registered Communications Distribution Designer – RCDDv14
Last Update: Dec 25, 2024
Questions: 288
RCDDv14 pdf

RCDDv14 PDF

$25.5  $84.99
RCDDv14 Engine

RCDDv14 Testing Engine

$30  $99.99
RCDDv14 PDF + Engine

RCDDv14 PDF + Testing Engine

$40.5  $134.99