For the 6-kVA UPS2000-G, a 1+1 parallel system requires () DB15 parallel cables to ensure that each UPS is connected by at least two parallel cables and to enhance the parallel system reliability.
The UPS5000-E can realize convenient and simple 2N power supply system only by configuring a ().
Which of the following functions do the FusionModule800 and Fusion Mod ule500 support? () (Multiple Choice)
Which of the following are the functions of the SCT configurator? () (Multiple Choice)
If the UPS is configured with thirty-two 12 V batteries, the floating charge voltage is ().
A UPS with a high input power factor allows for effective power grid utilization and reduced power grid interference. The input power factor of the UPS2000-A series (1 kVA to 3 kVA) is ().
Which of the following languages does the SCT configurator support? ( ) (Multiple Choice)
The capacity of the UPS5000-S power module is 50 kVA, and the height is 2U, which ranks the top in the power density of the industry.
Battery strings of different brands and the same capacity can be used in parallel.
The UPS5000-A has an industry-leading efficiency. It keeps a high efficiency within a wide load range, which greatly reduces the operating expense (OPEX) for clients. The highest efficiency can be().
The Fusion Mod ule500 and FusionModule800 must have unified network management software configured for remote WebUI monitoring.
Which of the following are the standard battery packs for the UPS2000-A-10KRTL? ( ) (Multiple Choice)
Which of the following statements are correct about the UPS5000-A (30-120 kVA) reliability? (Multiple Choice)
The UPS2000-G is a double conversion online UPS powered by mains in the normal operating state. A rectifier converts AC power into DC power, and then an inverter converts the rectified DC power into pure AC power to be supplied to loads. A charger is used to charge the storage battery string.
What differentiated features does the FusionModule800 have over competing products? () (Multiple Choice)
A cable of which the total carrying capacity is greater than the rated UPS current can satisfy the requirements of the project.
As the construction cost of the equipment room is high, reducing the floor area can efficiently save investment for clients. The floor area of a UPS5000-A-500K is ().
The UPS backup duration is typically within 30 minutes. It is reasonable to calculate the battery capacity with the galvanostatic method.
The output power factor of the UPS2000-G series (6 kVA to 20 kVA) is (), which adapts to new types of IT loads and greatly improves the system loading capability.
With parallel configuration, the UPS2000-G supports the use of a single () card for multiple UPSs in parallel. (Multiple Choice)
The UPS5000-E has strong load adaptability. It does not derate in case of leading/lagging capacitive/inductive loads.
The UPS2000-G series (6 kVAto 20 kVA) features an industry-leading lightning protection design, with a lightning protection level of () and a surge protection level of (), which avoids 90% of failures caused by lightning strikes and offers reliable protection for the AC input ports on back-end devices.
Electric cables are determined on actual project requirements during UPS configuration.
The standard components and features in the typical configuration solution of the FusionModule500 include ().
The number of battery strings for the UPS5000-A can be adjusted. To avoid replacing the whole battery string due to one faulty battery and solve the battery maintenance difficulty of traditional UPSs.
HCS-Pre-sales | H19-311 Questions Answers | H19-311 Test Prep | Huawei Certified Pre-sales Associate- Data Center Facility Questions PDF | H19-311 Online Exam | H19-311 Practice Test | H19-311 PDF | H19-311 Test Questions | H19-311 Study Material | H19-311 Exam Preparation | H19-311 Valid Dumps | H19-311 Real Questions | HCS-Pre-sales H19-311 Exam Questions