New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

CDCS EXIN EPI Certified Data Centre Specialist Questions and Answers

Questions 4

What is the minimum requirement for the power feeds to the building for a Rated-3 data center based on the ANSI/TIA-942 standard?

Options:

A.

Two feeds coming from two different substations, one power company is not acceptable

B.

Two feeds coming from two different substations, one power company is acceptable

C.

Two feeds entering the data center building from one substation

D.

One feed from one substation split over two separated distribution boards in separate rooms

Buy Now
Questions 5

Do you need to consider blast protection when designing a data center?

Options:

A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

Buy Now
Questions 6

What is the main reason to install Earth Leakage protection?

Options:

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

Buy Now
Questions 7

What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?

Options:

A.

Cables should be loosely organized to allow for movement and be latched at the connectors.

B.

Cables shall be tightly organized to the rack and trays to avoid movement.

C.

Cables can be organized in any way as it is not important.

D.

Cables should be replaced by busbar trunking.

Buy Now
Questions 8

When installing a raised floor, can we use a spirit level bar to level the floor?

Options:

A.

Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).

B.

No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.

C.

Yes, but spirit level bars can only be used in the vertical plane.

D.

Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.

Buy Now
Questions 9

An MCB needs to be installed in the PDU of an air-conditioner unit.

Which breaking curve should you select?

Options:

A.

D-Curve

B.

C-Curve

C.

B-Curve

D.

A-Curve

Buy Now
Questions 10

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?

Options:

A.

No influence as long as the temperature is at approximately 20°C/77°F

B.

Relative humidity has no influence on ESD

C.

ESD levels will go up

D.

ESD levels will go down

Buy Now
Questions 11

The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.

What action, if any, should you recommend for the computer room?

Options:

A.

Maintain the current wet pipe system.

B.

Replace the wet pipe system with a deluge system.

C.

Replace the wet pipe system with a dry pipe system.

D.

Replace the wet pipe system with a pre-action system.

Buy Now
Questions 12

The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?

Options:

A.

Rating - 4

B.

Rating - 3

C.

Rating - 2

D.

Rating - 1

Buy Now
Questions 13

You are working on the design of a new facility. The electrical riser of the building with high current power is located close to the area where sensitive IT equipment in the computer room will be located.

What should you recommend to reduce the amount of EMF coming from the electrical riser?

Options:

A.

Install single-phase power cabling

B.

Install three-phase power cabling based on three individual core wires

C.

Install bus bar trunking

D.

Install three-phase power cabling based on a combined cable (e.g. XLPE etc.)

Buy Now
Questions 14

You are allowed to use a calculator for this question. The total power consumption of the ICT equipment in a rack is 6 kW. The equipment is traditional ICT equipment with a Delta-T of approximately 11 °C / 20 °F. Calculate the approximate CFM required to cool the equipment in the rack.

Options:

A.

Approximately 1,500 CFM

B.

Approximately 1,000 CFM

C.

Approximately 500 CFM

D.

Approximately 160 CFM

Buy Now
Questions 15

What should be considered when installing overhead data cabling?

Options:

A.

To maintain minimum separation from power and ensure that the fire detection and suppression systems are not hindered.

B.

Copper data cabling should not be placed in metal cable trays.

C.

Optical fiber cabling should always be positioned on top of the copper cabling in the same cable tray to avoid damage to the sensitive optical fiber.

D.

All cabling should make sharp bends directly into the rack to avoid usage of additional space and blocking the airflow on top of the rack.

Buy Now
Questions 16

The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.

What is the most likely root cause?

Options:

A.

The cleaning crew is not doing their work properly

B.

Every computer room has high dust levels due to constant high-speed air movement

C.

Low pressure in the computer room

D.

Floorboards are most likely not fitted correctly

Buy Now
Questions 17

The noise levels in the data center are approximately 91 dB (A).

Do employers need to take precautions?

Options:

A.

No, anything less than 100 dB (A) is acceptable.

B.

There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.

C.

As long as the data is compliant to ISO/IEC 27001 it is acceptable.

D.

Yes, since it is mandated by regulations.

Buy Now
Questions 18

Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:

•Rated power: 30 kVA

•Rectifier input voltage: 400 V/3 phase

•Rectifier input power factor: 0.8

•Battery rated voltage: 384 V

•Number of cells: 192

•End of discharge voltage: 308 V

•Inverter output voltage: 400 V/3 phase

•Inverter output power factor: 0.8

What information is missing to perform the battery calculation?

Options:

A.

UPS efficiency

B.

Inverter efficiency

C.

Load imbalance on the phases

D.

Available battery charging current

Buy Now
Exam Code: CDCS
Exam Name: EXIN EPI Certified Data Centre Specialist
Last Update: Dec 25, 2024
Questions: 60
CDCS pdf

CDCS PDF

$25.5  $84.99
CDCS Engine

CDCS Testing Engine

$30  $99.99
CDCS PDF + Engine

CDCS PDF + Testing Engine

$40.5  $134.99