Black Friday Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

CCP Certified Cost Professional (CCP) Exam Questions and Answers

Questions 4

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Resource planning must take all of the following into account except:

Options:

A.

Types of materials, equipment and labor skills required to complete the project

B.

Cash flow (expenditures) limitations for completing work on the project

C.

Time available to complete the project

D.

Earned value techniques established for the project

Buy Now
Questions 5

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Fred Fiedler's contingency model suggests that:

Options:

A.

Leadership styles are just the opposite of the managerial grid model

B.

Successful leadership depends upon a good match

C.

between the style of the leader and the demands of the situation

D.

Successful leadership can always be imposed by experienced supervision

E.

A relationship oriented leader described the least preferred worker in an unfavorable light

Buy Now
Questions 6

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

A cyclical process model was chosen as the basis for total cost management (TCM) because:

Options:

A.

It is one of the basic tenets of quality improvement

B.

Refinement is needed to prepare the estimate at completion (EAC)

C.

Strategic assets and projects have inherent life cycles

D.

It facilitates development of budgets and schedules

Buy Now
Questions 7

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

Options:

A.

82%

B.

75%

C.

90%

D.

84%

Buy Now
Questions 8

After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

Is the percent complete stated by the contractor correct?

Options:

A.

No, it should be 55.0%

B.

No, it should be 50.0%

C.

No, it should be 52.5%

D.

Yes, it is 60%

Buy Now
Questions 9

Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?

Options:

A.

Productivity efficiency factor

B.

Value engineering

C.

Cash flow

D.

The learning curve

Buy Now
Questions 10

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Annual estimated tax would be:

Options:

A.

$3,869

B.

$5,565

C.

$10,500

D.

$11,925

Buy Now
Questions 11

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $10,000 is invested now at 10% compounded annually, what will the investments be worth 10 years from now?

Options:

A.

$25,940

B.

$29,450

C.

$21,345

D.

$16,180

Buy Now
Questions 12

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

Marketing has determined that XY2 can safely increase their per unit selling price to SO.55. The new break even amount for sales (in units) based on the new contribution margin is:

Options:

A.

40,000 units

B.

6,000 units

C.

50,000 units

D.

60,000 units

Buy Now
Questions 13

An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

Options:

A.

Costing

B.

Cost-price analysis

C.

Bid shopping

D.

Negotiating a best and final offer

Buy Now
Questions 14

What relationship more accurately defines a situation model of parallel activities that require a partial start of one activity?

Options:

A.

Start to start

B.

Star to finish

C.

Finish to start

D.

Finish to finish

Buy Now
Questions 15

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following calculations would not be needed to determine "net income?'

Options:

A.

Depreciation

B.

Taxes

C.

Present value

D.

Income before taxes

Buy Now
Questions 16

If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

Options:

A.

$2,424

B.

$2,976

C.

$2,688

D.

$2,697

Buy Now
Questions 17

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs amounting to $55.00/unit?

Options:

A.

22.22%

B.

$55.00

C.

2

D.

338.5

Buy Now
Questions 18

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The following question requires your selection of Scenario 1.4.162 from the right side of your split screen, using the drop down menu, to reference during your response/choice of response.

The budgeted cost work performed is;

Options:

A.

$90,000

B.

$100,000

C.

$95,000

D.

$108,000

Buy Now
Questions 19

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Why is a +/- notation necessary when developing an estimate?

Options:

A.

Contingency cushion

B.

It makes up for the lack of time to develop a real estimate

C.

It is a government requirement

D.

There are unknowns that affect the final cost of a project

Buy Now
Questions 20

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

Options:

A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Buy Now
Questions 21

A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

Options:

A.

Cost breakdown structure

B.

Code of accounts

C.

Cost estimate classification

D.

Schedule identification number

Buy Now
Questions 22

AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

Options:

A.

Risk analysis

B.

Benefit/Cost ratio (B/C) method

C.

Net present worth method

D.

Life cycle costs method (LCC)

Buy Now
Questions 23

Which of the following is a disadvantage to using target contract as a method of contracting?

Options:

A.

Encourages economic and speedy completion

B.

No opportunity to competitively bid the targets

C.

Almost immediate start on the work, even without scope definition

D.

Flexibility in controlling the work

Buy Now
Questions 24

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Based on the information provided, which statement is most correct?

Options:

A.

The truck should be leased

B.

The truck should be purchased

C.

The truck should not be leased

D.

The truck should not be purchased

Buy Now
Questions 25

When measuring progress using tasks that lack readily definable intermediate milestones and level of effort required is difficult to measure, the best methods to use is:

Options:

A.

Start/finish

B.

Weighted or equivalent units

C.

Incremental milestones

D.

Cost ratio

Buy Now
Questions 26

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

Options:

A.

8.7%

B.

8.2%

C.

4.6%

D.

8.0%

Buy Now
Questions 27

A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?

Options:

A.

1

B.

1.04

C.

0.89

D.

0.96

Buy Now
Questions 28

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the 25 year after tax present worth of this project?

Options:

A.

$13,738

B.

$137,466

C.

$(22,533)

D.

$22,533

Buy Now
Questions 29

____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.

Options:

A.

Soft logic

B.

Hard logic

C.

Deductive logic

D.

Inductive logic

Buy Now
Questions 30

Budgeted cost of work scheduled is all of the following except:

Options:

A.

Total costs incurred in accomplishing work in a given-time period

B.

Baseline for performance measurement

C.

Sum of the budgets for work scheduled

D.

Includes portion of the budget for level-of-effort work

Buy Now
Questions 31

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The compound interest factor used to determine Present Value in year number 5 is:

Options:

A.

0.3790

B.

0.6209

C.

1.6051

D.

0.6830

Buy Now
Questions 32

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

Options:

A.

Project is ahead of schedule, but over budget

B.

Project is behind schedule, but over budget

C.

Project is behind schedule, but under budget

D.

Project is ahead of schedule, but under budget

Buy Now
Questions 33

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

Options:

A.

ACWP/BCWS

B.

BCWS/BCWP

C.

ACWP/BCWP

D.

BCWP/ACWP

Buy Now
Questions 34

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following is least likely to improve a large earthmoving contractor's productivity?

Options:

A.

Using apprentice operators to save labor costs

B.

Starting summer work in the early morning hours to minimize work during peak heat periods of the day

C.

Remove underground hazards prior to excavation work

D.

Replacing old excavators with new, larger excavators

Buy Now
Questions 35

When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?

Options:

A.

For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.

B.

For changes in construction cost 'or varied works carried out beyond the original dale of completion

C.

In no situation

D.

For changes in The cost of resources beyond the control of either party

Buy Now
Questions 36

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

When analyzing a precedence diagram schedule, the "backward pass"

Options:

A.

Allows total float to be calculated

B.

Determines the duration of each activity

C.

Calculates the earliest allowable start and finish times for the activities in the schedule

D.

Allows activities to finish as soon as all their 'predecessor' relationships are satisfied

Buy Now
Questions 37

Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:

Options:

A.

Activity ID

B.

WBS Code

C.

Resource

D.

Account number

Buy Now
Questions 38

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

Options:

A.

$31,875

B.

$12,550

C.

$29,600

D.

$13,515

Buy Now
Questions 39

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

According to Maslow's hierarchy of needs, which level should be satisfied first?

Options:

A.

Physiological

B.

Self-actualization

C.

Safety needs

D.

Ego-status

Buy Now
Questions 40

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The main financial objective of many enterprises is:

Options:

A.

To maximize the total long-term economic return

B.

Subject to a well-conceived quality control plan

C.

To balance opportunities and risks

D.

Dependent on the backlog projects and the availability of resources

Buy Now
Questions 41

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, the final price for the piece of equipment will be:

Options:

A.

$328,810

B.

$370,710

C.

$375,658

D.

$378,750

Buy Now
Questions 42

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the cost performance index (CPI)?

Options:

A.

BCWP/ACWP = 105.000/110.000 = 0.95

B.

ACWP/BCWP = 110.000/105,000 = 1.05

C.

BCWS/ACWP = 100.000/110.000-0 91

D.

ACWP/BCWS = 110,000/100.000- 1.10

Buy Now
Questions 43

Which of the following is NOT a type of float?

Options:

A.

Total

B.

Negative

C.

Open end

D.

Free

Buy Now
Questions 44

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Taxes due at the end of year five (5) would be:

Options:

A.

$34,034

B.

$4,912

C.

$11,912

D.

$35,000

Buy Now
Questions 45

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The taxable income in year number 5 is:

Options:

A.

$17,543

B.

$121,551

C.

$42,543

D.

$125,00

Buy Now
Questions 46

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following methods a used for creating critical path schedules:

Options:

A.

Precedence diagram method

B.

Precedence and arrow diagram methods only

C.

Gantt chart (bar chart) method

D.

Arrow diagram method

Buy Now
Questions 47

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If $100,000 is needed to purchase a piece of equipment 3 years from now, how much money needs to be invested today assuming a 10% rate of return (rounded to the nearest thousand)?

Options:

A.

$78,000

B.

$70,000

C.

$75,000

D.

$82,000

Buy Now
Questions 48

You have recently been appointed as the Cost Engineer to oversee process improvement projects for a Discrete Part Manufacturer. You have been asked to calculate the CPI on a project initiated to implement a Value Stream Mapping Initiative. The accountant is only able to provide you with BAC and EAC figures of $ 5000 and 57500 respectively. The CPI is:

unable to be calculated from the information given

Options:

A.

<1

B.

=1

C.

=1

D.

>1

Buy Now
Questions 49

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Is a rise in the price level of a good or service, or market basket of goods and/or services.

Options:

A.

escalation

B.

deflation

C.

incremental costs

D.

inflation

Buy Now
Questions 50

Which of the following is a common technique to approximate the standard deviation?

Options:

A.

Range/4

B.

Range/16

C.

Range * 2

D.

Square root of the range

Buy Now
Questions 51

In the application of the benefit/cost method of analysis, what are the criteria for determining whether a proposed project is acceptable?

Options:

A.

B/C is - 1.0

B.

B/C is <1.0

C.

B/C is > minimum ROR

D.

B/C is >1.0

Buy Now
Questions 52

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The recognition of loss of value of a natural resource used in the production process is referred to as:

Options:

A.

Capital reduction

B.

Net loss

C.

Depreciation

D.

Depletion

Buy Now
Questions 53

Deliberate low bidding is often referred to as buying the job. Which of the following would not be a reason for low bidding?

Options:

A.

Survival

B.

Backing out of the bid competition

C.

Reducing cm eliminating competition

D.

Detecting significant errors in the purchaser's request for quote

Buy Now
Questions 54

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

All of the following are included in "income tax" calculations except:

Options:

A.

Annual income

B.

Annual expenditures

C.

Depreciation

D.

Initial cost of investment

Buy Now
Questions 55

_____________is defined as the budget for the cost (work) account times the percent complete for that account.

Options:

A.

Percent complete

B.

Forecast

C.

Cost to complete

D.

Earned value

Buy Now
Questions 56

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

Options:

A.

Recalculate the early finish for each activity

B.

Recalculate the early start for each activity

C.

Update the remaining duration for each activity

D.

Recalculate the critical path

Buy Now

AACE |

Exam Code: CCP
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Nov 24, 2024
Questions: 189
CCP pdf

CCP PDF

$25.5  $84.99
CCP Engine

CCP Testing Engine

$30  $99.99
CCP PDF + Engine

CCP PDF + Testing Engine

$40.5  $134.99