Pre-Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Questions 4

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Questions 5

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

Options:

Buy Now
Questions 6

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

Options:

Buy Now
Questions 7

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Buy Now
Questions 8

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

Options:

A.

Create an email group for the Solution Development Team to collaborate

on ideas.

B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.

C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.

D.

No action required as these employees are located in the same office.

Buy Now
Questions 9

A difference of opinion on the outcome of an earlier project has created a

'them and us' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

Options:

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.

Buy Now
Questions 10

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

'all members of the project understand and accept the DSDM approach'.

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Buy Now
Questions 11

The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in

the gardens could be enjoyed.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Deliver on time.

C.

Collaborate.

D.

Never compromise quality.

Buy Now
Questions 12

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Buy Now
Questions 13

There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as

it evolves.

Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2

can be used once, more than once or not at all.

Column 1

1) In order to get an objective

view, the financial transaction

function is to be tested by

someone from Finance who

has had no involvement in its

development.

2) Before the developer works on

the printing function for the

policy documents, the Sales

Manager will review a prototype

of the online application form

for the new coffee shop

insurance product with the

solution tester.

3) Security test scripts have been

provided by the company's

bank. These scripts will be used

to test the link from the

company's website to the

banking system, which is to be

developed specifically to achieve these tests

4.

The addition of the new coffee

shop insurance product may

threaten the stability of the

existing website. As a primary

route to market this is

unacceptable. The website's

capacity to run additional pages

is to be verified before any

other tests are performed.

5.

The Must Have and Should

Have requirements are to be

tested before the Could Have

requirements.

Column 2

    Collaborative Testing

    Repeatable Testing

    Independent Testing

    Prioritised Testing

    Test-Driven Development

Options:

Buy Now
Questions 14

How should the Project Manager assist the electricians to deliver the wiring?

Options:

A.

Provide separate electricians' rooms so they can focus on their work.

B.

Hold a weekly meeting for electricians so they can report on progress.

C.

Encourage the Business Ambassador to be available to discuss location of electrical sockets.

D.

Produce a detailed design of all electrical socket locations, to be approved by the Technical Co-ordinator.

Buy Now
Questions 15

A three-month timeframe has been specified to catch the seasonal sales window.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Buy Now
Questions 16

During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent

any Planning Authority issues.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because all stakeholders should attend the Daily Stand-up meetings.

B.

Yes, because each team member will have an opportunity to highlight any Planning Authority issues that may otherwise hinder their progress.

C.

No, because NOT all members of the Solution Development Team will attend the Daily Stand-up.

D.

No, because only members of the Solution Development Team should be permitted to attend Daily Stand-up meetings.

Buy Now
Questions 17

Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.

Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column

2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.

Each selection from Column 2 can be used once, more than once or not at all.

Options:

Buy Now
Questions 18

When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?

Options:

A.

Hints and tips on how to influence and persuade others.

B.

An understanding of the decision-making process.

C.

Background to the disagreement and the reasons for this.

D.

Empowerment to discuss any wider project issues that may arise during the workshop.

E.

A step-by-step guide to running an effective workshop.

Buy Now
Questions 19

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the

agreement of the team.

Which Agile principle MOST influences this course of action?

Options:

A.

Deliver on time.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Buy Now
Questions 20

During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what

needed to be done before these would be acceptable.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because this will enable the Solution Development Team to ensure they are on track to deliver a viable solution.

B.

Yes, because this allows each team member working in the Timebox to provide a short progress report and raise any issues that hinder their progress.

C.

No, because early and frequent visibility of the product features will maintain engagement with the stakeholders.

D.

No, because only members of the Solution Development Team are permitted to attend Review Sessions.

Buy Now
Questions 21

The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open

Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.

At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.

However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video

tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of

storage space on the company server and require minimal maintenance.

The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.

Remember to limit your answers to the number of selections requested in each question.

Which 2 individuals should the Facilitator invite to participate in the Workshop?

Options:

A.

Chief Executive (Steering Group)

B.

Representative for Earth Excavations (Solution Developer)

C.

Representative for Timber Tigers (Solution Developer)

D.

IT Operations Manager (Solution Development Team)

E.

Marketing Director (Business Visionary)

Buy Now
Questions 22

Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the

project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements explain why the Architecture Angels' Finance Director would be an appropriate Business Sponsor?

Options:

A.

Is able to delegate most of the required involvement to the Chief Accountant.

B.

Has been friends with the Architecture Angels' Chief Executive since school.

C.

Is the project budget holder.

D.

Is concerned about preventing the costs of refurbishment from escalating and affecting the operations of the company.

E.

Will not distract the Solution Development Team, as is usually too busy to be involved.

Buy Now
Questions 23

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying

controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

Options:

A.

Encourage the Marketing Director to attend the End of Timebox Review.

B.

Attend the next Daily Stand-up to raise an issue about the windows.

C.

Prepare a summary of progress against plan, for presentation at the review.

D.

Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Oct 17, 2024
Questions: 78
AgilePM-Practitioner pdf

AgilePM-Practitioner PDF

$28  $80
AgilePM-Practitioner Engine

AgilePM-Practitioner Testing Engine

$33.25  $95
AgilePM-Practitioner PDF + Engine

AgilePM-Practitioner PDF + Testing Engine

$45.5  $130