The Customer Services Manager used to work in a call center, answering customer calls. Concerned for staff wellness, this manager has decided to invite anyone who is finding the changes overwhelming to contact them directly so that they can arrange appropriate support.
Which preference does this behavior BEST display?
Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation
Which 2 statements explain why the Architecture Angels' Chief Accountant would be an appropriate Business Ambassador?
Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included
in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary
Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged
before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been
achieved.
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company's
bank. These scripts will be used
to test the link from the
company's website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website's
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open
Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video
tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of
storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent
any Planning Authority issues.
Is this an appropriate application of Agile Project Management for this project?
Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Feasibility Assessment?
The Change Manager has read Goleman's articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that
leadership style can improve organizational culture and performance as measured by staff surveys.
Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the
organization.
Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each
recommendation in Column 1, select from Column 2 the 'dimension' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be
used once, more than once or not at all.
Which information could be recorded on an ‘empathy map’ for the marketing staff?
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Is the measure requested by the Customer Services Director likely to be affected by any of the practical considerations of data analytics?
The Sales Manager is excited by the challenge to lead a pilot to upskill the sales team in the new capabilities. They will particularly enjoy coaching and spending time with team members.
Which preference does this behavior BEST display?
Answer the following question about different language style preferences
identified by Pashler et. al. using VARK preferences.
As part of the Capability and skills development workstream, the Human
Resources (HR) Manager is considering the training needs of staff
managers undertaking staff appraisals. The HR Manager is designing the
learning activities so that they will appeal to differing ways for receiving
and processing information.
Column 1 is a list of learning activities that could be used to develop the staff.
For each learning activity in Column 1, select from Column 2 the VARK
preference to which it relates. Each selection from Column 2 can be used
once, more than once or not at all.
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions.
Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.
The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director's leadership team in the UniCo building. At the last Operations' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.
Is this an appropriate approach to reward the brain in the need for 'status', and
why?
Which Facilities stakeholder is MOST likely to be placed within the ‘external’ segment for the relocation work of the Operational delivery processes workstream?
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions. Answer the following questions about the use of David Rock’s SCARF framework to increase the motivation for change.
One aim of the relocation is to develop a less hierarchical culture. The relocation team hear that staff believe managers are still getting special treatment in the allocation of desks. To mitigate this concern, they have planned for groups to move separately over a few weeks and have communicated details with each group independently.
Is this an appropriate approach to reward the brain in the need for ‘fairness,’ and why?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 Sales Team Leaders (TL) are likely to be the line leaders MOST engaged in implementing change, based on the actions that have occurred to date?
Sales staff failed to achieve last month’s sales targets when training in the mobile products and supporting sales systems and processes was first started. This month the sales team is working after hours and weekends to try to meet the current targets while developing the new skills needed. It is generally felt that this situation is unsustainable.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
'all members of the project understand and accept the DSDM approach'.
What action should the Project Manager take?
The Marketing Director has insisted that detailed requirements for the new
coffee bar insurance web pages should be clearly defined in the early phases
of the project.
What action should the Project Manager take?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Which 2 actions should the Business Visionary take to implement the new
Must Have requirement?
Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team?
An external web developer is to be contracted to create the new coffee bar
insurance area on the existing web site. The chosen web developer will only
agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?
Which 2 statements represent appropriate entries for the plan for Post-Project
activities?
Which 2 actions should the Workshop Facilitator take to implement the new
Must Have requirement?
AgilePM |