PSPO-I Professional Scrum Product Owner (PSPO I) Exam Questions and Answers

Questions 4

A Sprint Retrospective should be held:

(choose the best answer)

Options:

A.

Only when the Scrum Team determines it needs one.

B.

At the end of the last Sprint in a project or a release.

C.

At the end of each Sprint.

D.

At the beginning of each Sprint.

Buy Now
Questions 5

A Scrum Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what done means.

(choose the best two answers)

Options:

A.

No work is left to meet the Definition of Done.

B.

Whatever the Product Owner defines as quality.

C.

Ready for integration.

D.

Ready to be released to end users.

E.

All work the Developers are willing to do.

Buy Now
Questions 6

What does it mean for a Scrum Team to be cross-functional?

(choose the best answer)

Options:

A.

The Scrum Team includes not only developers but also business analysts, architects,and testers.

B.

The Scrum Team includes skilled individuals who together have all the skillsnecessary to create value each Sprint.

C.

Developers on the Scrum Team work closely with business analysts, architects,developers, and testers who are not on the team.

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts,architects, developers, and testers.

Buy Now
Questions 7

True or False: The Product Owner makes sure the correct stakeholders are invited to the Sprint Retrospective. They might have important instructions for team improvements.

Options:

A.

True

B.

False

Buy Now
Questions 8

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily

Scrum?

(choose the best two answers)

Options:

A.

An update of completed tasks and of the remaining work so the Scrum Mastercan plan the next day.

B.

An updated Scrum board to make Sprint progress transparent for thestakeholders.

C.

A status report for the upper management indicating what each individual hasdone, will be doing, and what is impeding him/her.

D.

Identification of impediments that may prevent the Developers from achievingthe Sprint Goal.

E.

A shared understanding of the most important work to be undertaken next toachieve the best possible progress toward the Sprint goal.

Buy Now
Questions 9

What are the two responsibilities of testers in a Scrum Team?

(choose the best two answers)

Options:

A.

Tracking quality metrics.

B.

Scrum has no " tester " role.

C.

Verifying the work of programmers.

D.

The Developers are responsible for quality.

E.

Finding bugs.

Buy Now
Questions 10

Which of these may a Scrum Team deliver at the end of a Sprint?

(choose the best answer)

Options:

A.

Failing unit tests, to identify acceptance tests for the next Sprint.

B.

A single document, if that is what management asked for.

C.

An Increment of software with minor known bugs in it.

D.

A valuable, useful Increment that meets the Definition of Done.

Buy Now
Questions 11

True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.

Options:

A.

True

B.

False

Buy Now
Questions 12

The length of a Sprint should be:

(choose the best answer)

Options:

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of the above.

Buy Now
Questions 13

You are the Scrum Master for four Scrum Teams working from the same Product Backlog

Several of the Developers come to you complaining that work identified for the upcoming two

Sprints will require full-time commitment from a specialist who is external to the teams.

What should the Scrum Master consider in this situation?

(choose the best two answers)

Options:

A.

The need to have enough work to keep all Developers busy.

B.

The benefit of Developers figuring out a solution for themselves.

C.

The desire to maintain a stable velocity.

D.

The ability of the Scrum Teams to produce integrated Increments.

Buy Now
Questions 14

Scrum requires that the Product Owner must use which of the following items?

(choose all that apply)

Options:

A.

Burndown chart.

B.

Feature burn-up.

C.

Critical Path Analysis.

D.

Project Gantt chart.

E.

None of the above.

Buy Now
Questions 15

What tactic should a Scrum Team use to divide a group of 100 people into multiple Scrum

Teams?

(choose the best answer)

Options:

A.

Ask the people to divide themselves into teams.

B.

Create teams based on their skills across multiple layers (such as database, UI,etc.).

C.

Ask the Product Owner to assign the people to teams.

Buy Now
Questions 16

In order to maximize the value of the product, a Product Owner needs awareness of the following: (choose the best answer)

Options:

A.

Competitive research.

B.

Customer feedback.

C.

Product vision.

D.

Forecasting and feasibility.

E.

All of the above.

F.

None of the above.

Buy Now
Questions 17

What happens if the Scrum Team cannot complete its work by the end of the Sprint?

(choose the best answer)

Options:

A.

The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

B.

The Sprint is extended and future Sprints use this new duration.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it does not happenagain.

Buy Now
Questions 18

User documentation is part of your Definition of Done. However, there are not enough technical

writers for all teams. Your Scrum Team does not have a technical writer. What should the

Scrum Team do?

(choose the best answer)

Options:

A.

The Developers on the Scrum Team should write the user documentation.

B.

Wait until you have a technical writer on your Scrum Team to take care of this.

C.

Form a separate team of technical writers that will work on an on-demand basis forthe various Product Owners. Work order will be first in, first out.

D.

Let the user documentation remain undone and accumulate until after the lastdevelopment Sprint. It will then be done by any available technical writers.

Buy Now
Questions 19

What is the responsibility of the Product Owner in crafting the Sprint Goal?

(choose the best answer)

Options:

A.

The Product Owner has no responsibility for the Sprint Goal. It is the soleresponsibility of the Developers.

B.

The Product Owner cannot attend Sprint Planning without having documented theSprint Goal in advance.

C.

The Product Owner should come to Sprint Planning with a business objective in mind and work with the Developers to craft the Sprint Goal.

D.

The Product Owner must work with stakeholders to set each Sprint ' s Goal.

E.

The Product Owner defines the scope for a Sprint and therefore also the Sprint Goal.

Buy Now
Questions 20

When does a Developer become accountable for an item in the Sprint Backlog?

(choose the best answer)

Options:

A.

During the Daily Scrum.

B.

As soon as a Developer on the Scrum Team can accommodate more work.

C.

Never. All Developers on the Scrum Team share accountability for items in the SprintBacklog.

D.

At Sprint Planning when all of the Sprint Backlog items are split evenly across theDevelopers.

Buy Now
Questions 21

Which approach is best for Scrum Teams in order to produce valuable Increments?

(choose the best answer)

Options:

A.

Each Developer works on the component where they feel that they can contribute.

B.

Each Scrum Team works on an independent set of components.

C.

Each Scrum Team is accountable for developing functionality from beginning to end.

D.

Each Scrum Member works only as an independent layer of the system.

Buy Now
Questions 22

How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?

(choose the best answer)

Options:

A.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint.

B.

As much as is required to meet the Scrum Team ' s Definition of Done.

C.

All development work and at least some testing.

D.

A proportional amount of time on analysis, design, development, and testing.

Buy Now
Questions 23

The job of a Product Owner focuses on the following:

(choose the best two answers)

Options:

A.

Working with customers and stakeholders to identify the most valuable productrequirements.

B.

Writing clear, transparent User Stories.

C.

Being with the Scrum Team all the time, just in case they need me to clarify arequirement.

D.

Clearly communicating project or release status and strategies to customers andstakeholders.

Buy Now
Questions 24

When multiple Scrum Teams are working on a single product, what best describes the

Definition of Done?

(choose the best answer)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed andreconciled during a hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all otherteams so the differences are known.

D.

When multiple Scrum Teams are working together on a product, they must mutuallydefine and comply with the same Definition of Done.

Buy Now
Questions 25

Which statement best describes the Sprint Review?

(choose the best answer)

Options:

A.

It is a mechanism to control the Developers activities during a Sprint.

B.

It is used to congratulate the Developers if they complete their forecast or to punishthe Developers if they fail to meet their forecast.

C.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint andfigure out what to do next.

D.

It is a demo at the end of the Sprint for everyone in the organization to check on thework done.

Buy Now
Questions 26

True or False: The Scrum Team is accountable for creating a valuable increment every Sprint.

Options:

A.

True

B.

False

Buy Now
Questions 27

Which outcome is expected as a Scrum Team matures?

(choose the best answer)

Options:

A.

The Sprint Retrospectives will grow to be longer than 4 hours.

B.

They will improve their Definition of Done to include more stringent criteria.

C.

A Scrum Master is no longer needed since they are a mature team now.

D.

There will be no need for a timeboxed Sprint.

E.

Sprint Reviews will no longer be needed.

Buy Now
Questions 28

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?

(choose the best answer)

Options:

A.

Find another Scrum Team to give the excess work to.

B.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

C.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

D.

Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.

Buy Now
Questions 29

When might a Sprint be cancelled?

(choose the best answer)

Options:

A.

When the Developers determine the product plan is infeasible.

B.

When it becomes clear that not everything will be finished by the end of the Sprint.

C.

When the sales department has an important new opportunity.

D.

When the Sprint Goal becomes obsolete.

Buy Now
Questions 30

Who should make sure everyone on the Scrum Team does their tasks for the Sprint?

(choose the best answer)

Options:

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Scrum Team.

E.

All of the above.

Buy Now
Questions 31

When does the second Sprint start?

(choose the best answer)

Options:

A.

After the customer completes acceptance testing of the first Sprint.

B.

Once the architectural changes for the second Sprint are approved by the seniorarchitect.

C.

Immediately after the first Sprint.

D.

After the Product Backlog items for the second Sprint have been selected.

Buy Now
Questions 32

True or False: During the Sprint Review the stakeholder ' s role is to reorder the Product Backlog.

Options:

A.

True

B.

False

Buy Now
Questions 33

How should a Scrum Team deal with non-functional requirements?

(choose the best answer)

Options:

A.

Manage them during the Integration Sprint prior to the Release Sprint.

B.

Assign them to the lead developers on the team.

C.

Ensure every Increment meets them.

D.

Make sure the release department understands these requirements, but it is not theScrum Team ' s responsibility.

Buy Now
Questions 34

True or False: Product Owners must specify complete acceptance criteria for a Product

Backlog item before the Developers can select the item in Sprint Planning.

Options:

A.

True

B.

False

Buy Now
Questions 35

What is the timebox for the Sprint Planning event?

(choose the best answer)

Options:

A.

Monthly.

B.

Whenever it is done.

C.

8 hours for a one-month Sprint.

D.

4 hours for a one-month Sprint.

Buy Now
Questions 36

When should the Product Owner update the project plan?

(choose the best answer)

Options:

A.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

B.

The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.

C.

After the Daily Scrum to ensure an accurate daily overview of project progress.

D.

The project plan must be updated prior to the Sprint Retrospective.

Buy Now
Questions 37

Which two ways of creating Scrum Teams are consistent with Scrum ' s values?

(choose the best two answers)

Options:

A.

Managers personally re-assign current subordinates to new teams.

B.

The Chief Product Owner determines the new team structures and assignments.

C.

Managers collaborate to assign individuals to specific teams.

D.

Existing teams propose how they would like to go about organizing into the newstructure.

E.

Bring all the people together and let them organize into Scrum Teams.

Buy Now
Questions 38

When Developers are having trouble delivering an Increment because they do not understand a

functional requirement, what should they do?

(choose the best answer)

Options:

A.

Partially complete the functionality, and discuss the remaining work at the SprintReview.

B.

Add a specialist to the Development Team.

C.

Collaborate with the Product Owner to determine what is possible and acceptable.

D.

Defer the work to a more appropriate Sprint.

Buy Now
Questions 39

Scrum requires that the Product Owner must use which of the following techniques?

(Choose the best answer)

Options:

A.

Feature burn-up.

B.

There is no required technique.

C.

Critical Path Analysis.

D.

Burndown chart.

Buy Now
Questions 40

Which of the following is required by Scrum?

(choose the best answer)

Options:

A.

Sprint Retrospective.

B.

Developers must stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release Planning.

E.

All of the above.

Buy Now
Questions 41

Who is accountable for tracking the remaining work toward the Sprint Goal?

(choose the best answer)

Options:

A.

The Developers.

B.

The Project Manager.

C.

The Product Owner.

D.

The Scrum Master.

Buy Now
Questions 42

What is the Product Owner responsible for during the Sprint Retrospective?

(choose the best answer)

Options:

A.

Summarizing and reporting the discussions to the stakeholders that they represent inthe Scrum Team.

B.

The Product Owner should not take part in Sprint Retrospective.

C.

Participating as a Scrum Team member.

D.

Capturing requirements for the Product Backlog.

Buy Now
Questions 43

A Product Owner is accountable for maximizing the value of the product that is the result of the work of the Scrum Team. Which of the following can be delegated to others, while the Product Owner remains accountable for the work?

(choose the best two answers)

Options:

A.

Attending the Sprint Retrospective.

B.

Attending the Sprint Review.

C.

Ordering Product Backlog items.

D.

Developing and communicating the Product Goal.

Buy Now
Questions 44

Which of the following are true about the length of the Sprint?

(choose the best answer)

Options:

A.

The length of the Sprint should be proportional to the work that is done in betweenSprints.

B.

All Sprints must be one month or less.

C.

Sprint length is determined during Sprint Planning, and should hold the time it willtake to build the planned features in the upcoming Sprint, but does not include timefor any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough tomake sure the Scrum Team can deliver what is to be accomplished in the upcomingSprint

Buy Now
Questions 45

True or False: To get started in terms of what to build, Scrum requires no more than a Product

Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum

Master to help guide the process.

Options:

A.

True

B.

False

Buy Now
Questions 46

What are two effective ways for a Scrum Team to ensure security concerns are satisfied? (choose the best two answers)

Options:

A.

Add security concerns to the Definition of Done.

B.

Delegate the work to the security department.

C.

Have the Scrum Team create Product Backlog items for each concern.

D.

Add a Sprint to specifically resolve all security concerns.

E.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

Buy Now
Questions 47

What might indicate to a Product Owner that she needs to work more with the Scrum Team?

(choose the best answer)

Options:

A.

The acceptance criteria do not appear to be complete.

B.

She is not working full time with the Scrum team.

C.

People leave the Scrum Team.

D.

The Increment presented at the Sprint Review does not reflect what she thought she had asked for.

Buy Now
Questions 48

Which two things should the Scrum Team do during the first Sprint?

(choose the best two answers)

Options:

A.

Make up a plan for the rest of the project.

B.

Define the major product features and a release plan architecture.

C.

Analyze, describe, and document the requirements for the subsequent Sprints.

D.

Build at least one piece of valuable functionality.

E.

Create at least one valuable, useful Increment.

Buy Now
Questions 49

How much of the Sprint Backlog must be defined during the Sprint Planning event?

(choose the best answer)

Options:

A.

Just enough to understand design and architectural implications.

B.

Enough so the Developers can create their forecast of what work they can do.

C.

The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.

D.

Just enough tasks for the Scrum Master to be confident in the Developers ' understanding of the Sprint.

Buy Now
Questions 50

Which of the following practices might help the Product Owner minimize waste in developing

and sustaining the Product Backlog?

(choose the best two answers)

Options:

A.

Avoid distracting the Scrum Team by maintaining newly gathered ProductBacklog items in a separate Product Backlog until they are fully understood.

B.

Hand off ownership of the Product Backlog to someone else.

C.

Remove items from the Product Backlog that have not been addressed in a longtime.

D.

Only fully describe Product Backlog items when it seems likely they will beimplemented.

Buy Now
Questions 51

Who starts the Daily Scrum?

(choose the best answer)

Options:

A.

The Scrum Master. This ensures that the Developers have the event, and it stayswithin the timebox.

B.

The person coming in last. This encourages people to be on time and helps to staywithin the timebox.

C.

The Product Owner.

D.

Whoever the Developers decide should start.

E.

The person who has the token.

Buy Now

PSPO |

Exam Code: PSPO-I
Exam Name: Professional Scrum Product Owner (PSPO I) Exam
Last Update: Apr 3, 2026
Questions: 173
PSPO-I pdf

PSPO-I PDF

$25.5  $84.99
PSPO-I Engine

PSPO-I Testing Engine

$30  $99.99
PSPO-I PDF + Engine

PSPO-I PDF + Testing Engine

$40.5  $134.99