PSK-I Professional Scrum with Kanban (PSK 1) Exam Questions and Answers

Questions 4

Which of these statements about Sprints and Kanban is NOT correct?

(choose the best answer)

Options:

A.

The Sprint is an example of a cadence.

B.

A Scrum Team will eventually stop using Sprints if they correctly implement Kanban.

C.

The Sprint is an example of limiting Work in Progress (WIP).

D.

The Sprint is an example of an explicit policy for how a team is working.

Buy Now
Questions 5

What is the best use for the Work Item Aging metric?

(Choose the best two answers)

Options:

A.

To influence the Scrum Team’s SLE.

B.

To help the Developers inspect and adapt their Sprint in the Daily Scrum.

C.

As a leading indicator to the length of the feedback loop for that Work Item.

D.

As an indicator of the Work Item size.

E.

To help the Scrum Team inspect and adapt their process and Definition of Workflow in their Retrospective.

Buy Now
Questions 6

What is the flow metric used to forecast how many items will be done for a date?

Options:

A.

Lead time.

B.

Work in Progress (WIP).

C.

Cycle Time.

D.

Throughput.

Buy Now
Questions 7

When the Developers limit Work in Progress (WIP) inside a Sprint, what would you expect to observe?

(Choose the best three answers)

Options:

A.

The Developers would stop beginning work, and instead, start finishing work.

B.

The amount of work done by the end of the Sprint would be reduced.

C.

Increased collaboration/swarming between the Developers.

D.

Self-management would be strengthened as a result of increased transparency.

Buy Now
Questions 8

How do Work in Progress (WIP) Limits relate to self-management?

(choose the best two answers)

Options:

A.

WIP Limits inhibit self-management since they limit the team's autonomy to pull

work.

B.

WIP Limits provide a boundary/container in which the Scrum Team self-

manages.

C.

A Scrum Master defines a WIP Limit to help the Scrum Team self-manage.

D.

As part of self-managing, Scrum Teams figure out their own WIP Limits.

Buy Now
Questions 9

True or False: If you reduce your batch size, your overall efficiency will always increase.

Options:

A.

True

B.

False

Buy Now
Questions 10

True or False: Work Item Age is a leading indicator for the length of the Scrum Team's

feedback loop for that (in progress) item.

Options:

A.

True

B.

False

Buy Now
Questions 11

Which of these statements are true about Kanban and the Scrum theory of empiricism?

(choose the best two answers)

Options:

A.

The Kanban board provides Scrum Teams with transparency that helps them

inspect and adapt their process.

B.

Kanban metrics are used in the Sprint Review to allow the Product Owner to

inspect the Throughput and adapt the Scrum Team's Cycle Time.

C.

Kanban helps Scrum Teams deal with simple and complicated work where

empiricism is not necessary.

D.

Kanban helps Scrum Teams achieve faster, healthier flow. That brings more

rapid transparency about the product, enabling a more effective inspection and

adaptation loop.

Buy Now
Questions 12

Which of these is NOT a good description of Cycle Time?

(choose the best answer)

Options:

A.

The time a work item takes from initial idea/concept to feedback returned from

customers after a production release.

B.

The length of time a work item stays in one column.

C.

The number of items that move into the delivery/end point per time period (e.g.,

daily/weekly).

D.

The time a work item starts until when it finishes.

Buy Now
Questions 13

Which of the following statements about supplementing Scrum with Kanban practices is true?

(choose the best answer)

Options:

A.

Scrum Teams may choose to skip the Sprint Planning event.

B.

It encourages team collaboration/swarming.

C.

It applies primarily to maintenance type of work.

D.

It implies that the Scrum Team must have a sequential approach to work.

Buy Now
Questions 14

What is the best chart to determine when a single item that has not been started will be

finished?

(choose the best answer)

Options:

A.

Cycle Time scatterplot.

B.

Cumulative Flow diagram (CFD).

C.

Throughput run chart.

D.

WIP Aging chart.

Buy Now
Questions 15

A Service Level Expectation (SLE) forecast is a calculation about the future completion of an item that includes two things. What are those two things?

(Choose the best two answers)

Options:

A.

A commitment.

B.

A probability.

C.

A velocity.

D.

A range of elapsed days.

Buy Now
Questions 16

Who must change the Work in Progress (WIP) Limits in the Definition of Workflow when urgent

work emerges from the Sprint?

(choose the best answer)

Options:

A.

The Developers.

B.

The Product Owner.

C.

The Scrum Master.

D.

No one. Urgent work is not a reason to change WIP Limits.

E.

No one. WIP Limits cannot be modified during a Sprint.

Buy Now
Questions 17

True or False: When the Developers add Kanban to Scrum, the way they use the Sprint Goal

during their Daily Scrum changes.

Options:

A.

True

B.

False

Buy Now
Questions 18

In the context of Scrum, which of the following statements about Cycle Time are true?

(Choose the best two answers)

Options:

A.

Cycle Time should be exactly the length of a Sprint.

B.

Cycle Time for some Product Backlog items might be longer than a length of Sprint.

C.

Average Cycle Time should be shorter than a length of Sprint.

Buy Now
Questions 19

Which of the following are Kanban practices for Scrum?

(choose the best answer)

Options:

A.

Visualizing flow, limiting WIP, actively managing the Work in Progress (WIP),

inspecting & adapting the Workflow.

B.

Kaizen, remove delays, visualize policies, pull system.

C.

Small batches, limit WIP, eliminate waste, Kaizen.

D.

Class of service, cost of delay, visualize the Workflow, limit WIP, manage flow.

E.

T-shirt size estimation, service level expectations, limit WIP.

Buy Now
Questions 20

When the Developers limit Work in Progress (WIP) inside a Sprint, what would you expect to

observe?

(choose the best three answers)

Options:

A.

The Developers would stop beginning work, and instead, start finishing work.

B.

The amount of work done by the end of the Sprint would be reduced.

C.

Self-management would be strengthened as a result of increased transparency.

D.

Increased collaboration/swarming between the Developers.

Buy Now
Questions 21

What is Kanban?

(choose the best answer)

Options:

A.

A methodology aimed at visualizing your Workflow for effectiveness and enhance

productivity within the team.

B.

A strategy for optimizing the flow of value through a process that uses a visual, Work

in Progress (WIP) limited pull system.

C.

A set of practices that are additive to the Scrum framework.

D.

None of the above.

Buy Now
Exam Code: PSK-I
Exam Name: Professional Scrum with Kanban (PSK 1) Exam
Last Update: Feb 5, 2025
Questions: 73
PSK-I pdf

PSK-I PDF

$29.75  $84.99
PSK-I Engine

PSK-I Testing Engine

$35  $99.99
PSK-I PDF + Engine

PSK-I PDF + Testing Engine

$47.25  $134.99