A business analyst (BA) conducts a process analysis on the business analysis practices that were used on the previous major implementation. From this the BA identifies and documents that there are three improvement areas which would make the business analysis process more efficient In which business analysis artifact does the BA document these measures of improvement for the next piece of analysis work?
A business analyst (BA) working on a recently implemented project is approached by the sponsor to provide artifacts that can be used organization wide for the long -term. Which of the following should the BA provide?
The business analyst (BA) presented a concept model during a requirements walk through to the project sponsor, implementation subject matter expert and operational support start. While the presentation was clear to the project sponsor the other stakeholders were unsure about the impacts to their respective daily tasks. What should the BA include in the next walk through, so that all stakeholders have a better understanding of the requirements?
The business sponsor of a project to automate a high risk, high profile process has expressed concerns that some activities people perform will be missed. The business analyst (BA) has already created a process flow with associated user stories.
Which of the following actions will address the sponsor’s concerns?
A business analyst (BA) has completed requirements elicitation and modeling on a project to implement a new case management system. During analysis of the requirements, the BA notices that one of the requirements appears to be in conflict with the company's case management policies. What should the BA do?
A business analyst (BA) finds conflicting requirements gathered from several stakeholders. Aside from interviews what additional activities can the BA use to safeguard against this happening?
You are the business analyst for your organization and are working on organizing the identified requirements for a new solution. Nancy, your assistant in this process, says that these requirements aren't very complex. You agree but add that it's this thing that makes the overall solution complex.
What thing adds to the level of complexity among requirements?
Which one of the following business analysis planning and monitoring techniques can be used to define and document the business analysis approach?
Which of the following techniques is used to divide a project into controllable parts?
Henry is the business analyst for the UUH Organization. Currently Henry is working on several work products as part of the requirements development process. He may need to share these work products with the stakeholders.
Which of the following is not an example of a work product?
A business analyst (BA) is assigned to a project which has two main stakeholders: a highly regulated government agency and a less formal private company. To select the business analysis approach, the BA mi! conduct a meeting with representatives from each entity to decide on the level of formally needed for requirements and design specifications. During the meeting, what should the BA’s strategy be?
During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the Business analyst (BA). The BA became aware of the new functionality after a defect was raised against another component of the design. The BA can keep this situation from occurring in the future by creating a:
You are coaching Marcy, a new business analyst for your organization, on business analysis processes. Marcy is concerned about the define solution scope process, especially the implementation approach element.
Which of the following statements best defines the implementation approach element for Marcy?
Which of the following is described in the statement below?
"It shows the history and pattern of variation. It is a line graph that shows data points plotted in the order in which they occur. They show trends in a process over time, variation over time, or declines or improvements in a process over time. Trend analysis is performed using them."
You have identified a task in your task list that cannot be completed until the inspector for the project signs off on the initial deliverables.
The inspector's signoff on the initial deliverables is called what?
You are the business analyst for the NGQ Company. Management is concerned that their company is not able to meet an identified business need with their current existing structure, people, processes and technology. They've asked you to complete an analysis of their organization's ability to meet the identified business need.
What business analysis process are you completing for your organization?
In a requirements management effort, the business analyst (BA) has reviewed all the requirements and has completed assessing the various impacts of changes to some of the requirements. The BA is planning to share the impact of the changes to the stakeholders and obtain a consensus in resolution of some of the changes. Which technique will help the Ba obtain a resolution on the impact of the requirement changes?
You need to identify assumptions as part of the assessment of capability gaps.
Which of the following is an example of an assumption?
Your organization uses the MoSCoW approach to requirements prioritization.
What does MoSCoW mean?
A service provider has seen significant erosion of its profit margin so engages an external consultancy firm to assess its business operations and recommend options to improve profitability. What is the first step that the business analyst (BA) will perform as part of this engagement?
A customer has provided a business analyst (BA) with many business requirements and some have inter-dependencies with other requirements. To ensure the requirements are delivered according to customer expectations which requirements attribute should the BA consider including in the project requirements document?
A busmen analyst (BA) is assigned a new project to improve a delivery process. Which of the following does the BA create as an output of the initial meeting with experts?
A business analyst (BA) had identified redundancy in the process for the first contact resolution for customer issues: currently two separate a visions handle this task. A new solution identifies a single point of contact that will eliminate the redundancy. What can the BA do to highlight the required changes to the structure?
A company is about to embark upon a large organizational change initiative that involves restructuring its service offerings. A senior business analyst (BA) is assigned the work of establishing performance measures for the business analysis work to be performed by the 6A ream. Which of the following performance measures is appropriate to assess the value delivered by the work products against the cost time, and resource investments expended to create them?
A business analyst (BA) conducts a Business rules analysts exercise to identity the organizational rules constraining the project in addition to existing regulations and contracts. what else does the BA check?
A business analyst (BA) is preparing a requirement package for access management system. A state diagram foe entity 'User* has been prepared. The BA wants to check the completeness of requirements by comparing different models. Which diagram should be used with a state diagram to verity that all functions are defined to work with entity "User" for the different roles?
You are the business analyst for your organization and you are preparing the business case for a proposed solution. You need to include the management horizon in your business case.
What is the management horizon?
You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved.
What is management asking you to create?
Management has asked you, a business analyst for your organization, to create the solution scope for an identified problem. In order to complete this task, you'll need three elements.
All of the following are elements you'll need in order to write the solution scope except for which one?
The business analysis approach generally defines all of the following attributes except for which one?
You are the business analyst for your organization. You are preparing the business needs documentation for a new solution to an identified problem. Parts of your input for this process are the business goals and
objectives set by your organization.
What approach can you use to assess the business goal and their validity and longevity?
Paul has been asked to complete SWOT analysis for his solution scope. What does SWOT analysis mean?
You are completing enterprise analysis. Management has asked you to create a document that will help them create a go/no go decision to invest and more forward with a proposed project.
What document does management want you to create?
What part of defining the business needs process will evaluate the ends that the organization is seeking to achieve?
You are working with several business analysts to determine the solution approach for an identified problem.
All of the following techniques are acceptable for identifying the solution approach except for which one?
What plan will describe the stakeholder groups, communication needs, and the level of formality that is appropriate for the requirements?
You are the business analyst for your organization. Management realizes that a proposed solution has risks that may cause the entire project to fail. They would like you to prioritize the requirements with maximum risks first so that if the project fails, there is little loss of capital in the project implementation.
What requirements prioritization approach is management asking you to create in this instance?
You are the business analyst for your organization. A customer has approached your organization and is requesting that your company create new software for them that will help them collect customer information.
In regard to enterprise analysis this business needs stems from which one of the following need generation approaches?
You are creating a model for your requirements.
Which model type categorizes and describes the people who directly interact with a solution?
Which one of the following terms is not a business analysis planning and monitoring approach?
Some of the requirements in the solution must be completed because of laws and regulations in your industry. Management would like you, the business analyst, to rank the requirements according to the relevant laws.
What type of requirements prioritization is management having you complete?
You are the business analyst for your organization and working with the stakeholders to prioritize the requirements. The stakeholders are concerned about the financial impact of the requirements should some of them fail during the implementation. You would like to rank the risk tolerance of the stakeholders based on their comments about the solution and the requirements.
The following are the three categories of risk tolerance associated with the stakeholders except for which one?
Holly's organization uses a plan-driven approach to business analysis.
When it comes to communication in Holly's organization what type of communication will likely be required?
You are the business analyst for a solution that has 435 stakeholders.
How many communication channels exist in this project?
Wanda is the business analyst for her organization and she is currently working on the specify and model requirements process. One of the elements of this process is the documentation of the textual requirements.
Wanda must describe the capabilities of the solution, any conditions that must exist for the requirements to operate, and what third component of the textual requirement?
What business analysis element tries to identify as many potential options as possible to meet the business objectives and fill identified gaps in capabilities?
You are the business analyst for your organization. Management wants you to prioritize the identified requirements by the requirements that have the highest likelihood of success.
Why would management want you to prioritize the requirements with this factor even though some of the requirements may be difficult to implement?
What business analysis plan defines the process to be followed in managing the solution scope and requirements?
is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.
You are the business analyst for your organization and are working with Ralph who is also a business analyst at your company. You have moved one of the requirements higher in the prioritization of the requirements because it is needed to be implemented before some of the more important requirements are done. Ralph disagrees with your placement of the requirement because you are to rank the requirements based on their level of difficulty.
Who is correct and why?
You are the business analyst for a large, complex solution and you are working with the stakeholders to determine the prioritization of the requirements. You would like to use the decision analysis to determine the best decision for the requirements outcome. You must know four things as part of decision analysis.
Which one of the following will not help you with this approach to the requirements prioritization process?
You are the business analyst for your organization and are working on a solution that will connect several databases to a web application. You are concerned that the databases may not be operable with the software solution a programmer is recommending.
What requirements elicitation technique can help you determine the interoperability of the software, the databases, and the web application?
Which of the following reports is generated whenever the project is slipping off the project schedule and includes an of the problem?
Enterprise analysis provides many things for an organization.
All of the following are tasks included in enterprise analysis except for which one?
You are the business analyst for your organization. You are currently writing the business goals and objectives as part of the elements for the define business process.
Which one of the following statements best describes the business goals and objectives element?
Gina has been asked to provide decision analysis for her solution scope.
Which one of the following best describes the decision analysis technique?
You have completed the requirements documentation and the stakeholders have signed off on the requirements. Now the requirements are advancing into a project as your organization has chartered a project based on the identified requirements.
What stakeholder is now responsible for assessing the solution scope to determine the project scope?
Martha is observing Sarah complete several complex steps as part of her business analysis requirements elicitation process. In this instance Martha working alongside Sarah is actually helping Sarah complete the work so that Martha can understand all of the steps Sarah must complete.
What type of requirements elicitation technique is Martha using?
You are completing the requirements for vendor selection and need to create a procurement form that will ask the vendor to provide only a price for commercial-off-the-shelf solution.
What type of procurement form will you need to provide to the vendor?
Which of the following models demonstrates the attributes, operations, and relationship to entities within the solution?
Which of the following techniques involves determining and documenting the variance between business requirements and current capabilities?
You are creating a model that shows how data moves through a system. Each function that modifies the data in any manner is identified, decomposed to smaller levels, and the system is completely described from start to storage.
What type of a modeling technique are you using in this scenario?
Holly is the business analyst for her organization. Holly encourages teamwork and open communications among the business analysis team and the stakeholders. She wants stakeholders to drop by her office and freely discuss the requirements, the solution scope, and other concerns about the solution she's working on. Holly definitely prefers informal communications.
What is the danger Holly may experience with informal communications?
You are the business analyst for your organization and are trying to determine the best solution for an identified problem. You have determined that you could create a software solution using inhouse resources for
$65,000 and with an ongoing support of $5,600 per month. A vendor offers you a quote that they can create the software for $49,000 with an ongoing support of $6,100 per month.
Which solution should you choose?
You are the business analyst for your organization and are preparing for the conduct elicitation activities. You'll have six inputs as you prepare for this activity.
Which one of the following is not a valid input for the requirements elicitation activity?
Which conduct stakeholder analysis technique is useful for identifying shared characteristics of a stakeholder group?
You are the business analyst for your organization. You have identified the costs and level of effort needed for
each of the solution components. Management has asked that you also assess the most effective tradeoffs between delivery options. You consider the available resources and the constraints on the solution to determine if an additional investment is justified to realize a higher value for the solution.
What other consideration could you include in your assessment of the solution?
You are preparing the business case for a proposed solution in your organization. You need to identify several components for the business case including an assessment of the risks the solution may contain.
Which one of the following is the best definition of a risk as it pertains to the business case?
Management would like you to front-load the requirements with the most risk requirements.
Why would management prefer the risky requirements first in the prioritization?
Which of the following inputs of Monitor and Control Risks acquires information from performance measurements and evaluates it to provide variance analysis and forecasting?
Which of the following is a quality control chart to track trends in project execution?
Bob and Susan are business analysts for their organization. They are examining two materials that could be used in an upcoming project. They aretesting the materials and measuring the results of each test to compare the materials to each other. This process will help Bob and Susan determine which material is best for their upcoming project.
What type of process are Bob and Susan completing with these materials?
You are the business analyst for your organization. As part of the requirements prioritization you have given each key stakeholder $10,000 in play money to distribute among the identified requirements. Each stakeholder can assign their play money to any of the requirements, but the requirementswill be prioritized based on the value of the play money assigned to each requirement.
What type of requirements prioritization is happening in this scenario?
As part of the requirements analysis a business analyst can use the same tools and techniques to model the current state of an organization.
All of the following are valid reasons why would a business analyst want to create a current state domain model except for which one?
Yolanda is the web designer for your company and you are the business analyst. You are working with Yolanda on a new website that your company will host. You'd like for her to create a mock-up of the website without spending much time on the actual workings behind the web interface. You'd like for her to show the customer how the website will look, some idea of the functionality of the website, and some basic graphics and colors so the customer can see the direction of the project.
What type of prototype are you asking Yolanda to create?
Which of the following tasks does not rely on other activities, and no other activities rely on this task completing?
You are the business analyst for your organization and are training Tracy on business analysis duties. You are explaining to Tracy how it's important for a business analyst to generate new ideas to approaching problems, solving problems, and to generate alternative solutions. You stress that it's important for the business analyst to generate new ideas and innovative concepts.
What type of analytical thinking are you describing for Tracy?
During a prioritization meeting, a business analyst (BA) mentioned that the access management system requirements are not stable. The project manager and a team lead proposed removing the requirements from discussion. A domain subject matter expert (SME) insisted on making that requirement a high priority, because it is really important from their point of view.
What should the BA do?
A business analyst (BA) works for an organization that is moving from a waterfall methodology to an agile approach. This causes new challenges and opportunities for the BA.
Which business analysis planning and monitoring element is most impacted by the organization's change?
A solution implemented three months ago has decreased performance as the volume of transactions has increased. A business analyst (BA) is tasked with analyzing the performance of the application and providing recommendations.
What actions does the BA need to take?
A business analyst (BA) has been assigned to manage the ongoing stakeholder collaboration after completing a project. The BA needs to understand the stakeholders' level of satisfaction and wants to offer stakeholders an opportunity to help improve the working relationships based on this information.
Which technique should the BA use?
A non-profit utility company has 900 employees, a majority of whom are hourly employees and must track their time using a paper based process. A few years ago, the Director of Human Resources purchased a software system to eliminate the current paper-based time reporting process. No requirements specific to the utility company were defined prior to the purchase. A team was formed to implement the software During implementation process, the team discovered the software lacked functionality and was not robust enough to support the general ledger requirements The company stopped the effort and incurred a $500,000 USD loss on the cost of the software.
This year, the Director of Finance requested that a team investigate the current paper-based time reporting process and recommend solutions. The Director of Finance feels that the Director of Human Resources must be involved as a critical stakeholder. The Director of Human Resources is still bitter about the last effort because the process stopped'.
Which of the following is included in performing a stakeholder analysis?
A business analyst (BA) is planning for an upcoming solution based on a signed contract with a client but has learned that one of the key subject matter experts is unavailable during the first half of the business analysis phase. The project has a tight timeline and firm deadline that is part of the contract. There are no substitutes for the key subject matter expert.
How should the BA proceed?
A business analyst (BA) is reviewing the performance results from a recent change initiative. One of the results stated, "The planned schedule expected 50% of the project to be done at milestone 6. The schedule performance index (SPI) was .87. Three project team members worked overtime to ensure that the actual schedule would align with the planned schedule."
This is an example of what type of action?
An organization has a procedure for receiving requests from its customers: investigating each and then replying with an answer. The general manager asks a business analyst (BA) to identify ways to improve the current practice because it takes too long for the requests to be answered.
Which of the following techniques will the BA use to review the tasks?
A popular department store chain wants to make computer upgrades as well as conduct a major remodeling effort to increase revenue to all their 100 stores over the next 2 years. The remodeling will occur in two phases. The two phases are required at each store and can be completed in any order, but each phase must be fully completed before the next phase can begin. Phase 1 will take approximately 32 weeks and will not require a store to be temporarily closed. Phase 2 will take approximately 20 weeks and will require a store to be temporarily closed.
In order to keep inventory level and total revenue for the department store chain at an operational level, 75% of the stores must remain open to the public at all times. Against the board of director's advice, the Chief
Executive Officer (CEO) made a decision to start and complete the top 25 revenue-producing stores in the first year to get those stores remodeled and fully operational.
A business analyst (BA) has been brought in to help with planning the project and gathering requirements. Based on the CEO's executive decision, which risk tolerance attitude is the CEO exhibiting?
A health insurance provider undertakes enhancements to its mobile application platform and finalizes the following capabilities as part of the scope of the next release:
I.Ability to integrate online maps and global positioning system (GPS) technology with the mobile application in real time to display location of service providers in the subscriber's vicinity that participate in the subscriber's plan network.
II.Ability for the subscriber to lookup the service providers by specifying either a postal code or a search area radius in miles.
III.Ability for the subscriber to initiate the download of fee information for one or more service providers in a single request.
Through requirements workshops the business analyst elicits the following detailed business requirements:
1.The company's mobile application platform must support real time integration with the following third party systems:
A ) GPS System
B ) Postal Code Validation
2.The service providers available for selection must participate in the subscriber's medical plan network as of the current system date.
3.The map display shall highlight the boundary of the search area with a dotted yellow line.
4.The extent and shape of the search area shall be determined based on one of the following user choices:
A ) Postal code – Subscriber location acquired from GPS shall be used to determine and populate the related postal code as the default postal code with options for the user to change the postal code.
B ) Radius for the search area around the subscriber's location, that will have default value of 5 miles. The radius can be changed by the subscriber with a maximum range of 50 miles.
5.Subscriber shall be able to select one of the options above and supply corresponding input.
6.System shall validate the user input and display appropriate error messages if invalid.
7.Based on the inputs and the plan of the subscriber, the system shall retrieve information for the participating service providers that are located within the designated search area.
8.System shall display a map including visual markers to indicate locations of the service providers in the top half of the device screen and a list of the same service providers in the bottom half of the device screen.
9.The list of service providers shall include the Name, Phone Number and Street Address.
10.If the subscriber specified the radius or retained the default postal code for the search area, the list shall additionally include the approximate driving distance in miles from the subscriber's last registered location and the list shall be sorted in the ascending order of the driving distance.
11.The subscriber shall be able to select a service provider either from the list or from the map and download a document that contains the name, contact telephone, email address, fax number and the fee schedule for
the covered services applicable to the subscriber's plan.
Which of the following relationship types correctly identifies the nature of the relationship between the 3 business capabilities and the 11 requirements?
A business analyst (BA) has been given a defect during user acceptance testing. After analyzing the defect, the BA determines it is a change in the requirement.
What does the BA need to do to assess the change?
A software development company is in the process of creating a new product for their customer base. It has been several years since such a project has been initiated and the organization has created a new team to own and develop the product. The project team will be evaluated by the successful adoption of the product, which will be developed over the next 12 months.
The team's business analyst (BA) has analyzed the current state in partnership with the product owner and has been meeting with senior management to identify the goals that need to be attained. A broad view of the business has been analyzed in order to have an understanding of how the company is currently providing value to its customer base.
What has the BA evaluated to help determine value of the project?
The BA is analyzing the requirements that are represented in the Class Diagram. In addition to the diagram, the BA would like to include a separate document that has the information about the data elements to ensure a common understanding of the classes' attributes. What technique is used to define the data elements?
Company A is a nation-wide leader in commercial demolition. Having just celebrated its 100th year of operations, the company decided to begin doing work internationally. The current system used for reporting company finances is unable to keep pace with the potential demands of doing work in geographically dispersed locations. Therefore, the company decided to replace its client-based Profit & Loss (P&L) reporting system with a more robust, web-based system. This will ensure transparency across the organization and enable better decision making.
The business analyst (BA) at Company A has recently completed several rounds of elicitation to determine the requirements for the new, web-based system. Over 1250 requirements were elicited. An initial Requirements Traceability Matrix (RTM) has been drafted, and a subset of the RTM can be seen below:
The risk associated with Requirement ID F-P0001 is HIGH. The BA has gone back to the Crew Chief to determine why this requirement's risk is HIGH. The Crew Chief stated that it was based on an assumption.
Which of the following assumptions would make this requirement's risk high?
A business analyst (BA) is working on a payment system (PS) implementation. A set of systems which should interact with a new system has been identified. The business analyst defined that a user with role of "Supervisor" in the PS must pass a two-factor authentication before an execution of the functions: "Change system parameters" and "Set up new supervisor." A user must have the role of "Supervisor" to use the standard functions "Send mail notification" or "Send SMS notification".
The BA defined the following use cases:
•"Change system parameters"
•"Setup new supervisor"
•"Send mail notification"
•"Send SMS notification"
•"Send notification"
•"Pass a two-factor authentication"
The BA wants to create a Use Case diagram.
Which technique should be used to define a communications protocol between the PS and other systems?
A company that specialized in manufacturing vending machines for books has been in business for 10 years. As the e-book and online retailing grow, the company perceived that a change is required to respond to the new emerging market forces. However, the change should focus on reusability as much as possible to reduce expenses. After analyzing the current state with the business subject matter experts, the business analyst
(BA) proposed investing in a new business line of vending machines that sell pay per use mobile device phone fast charging stations.
Due to the urgency of this change, the BA was asked to finalize requirements elicitation in the shortest possible time.
By proposing this change, what type of view did the BA use to analyze the current manufacturer's state?
An organization implements a solution to increase the efficiency of its internal processes. The business analyst (BA) felt that the success of the solution is tied to the organizational structure and confirmed that the solution conforms to the organizational hierarchy. After the solution rolled out, the solution was not widely adopted among stakeholders and some features were not being utilized.
Which aspect of the organizational structure did the BA fail to consider?
A non-profit utility company has 900 employees, a majority of whom are hourly employees and must track their time using a paper based process. A few years ago, the Director of Human Resources purchased a software system to eliminate the current paper-based time reporting process. No requirements specific to the utility company were defined prior to the purchase. A team was formed to implement the software. During implementation process, the team discovered the software lacked functionality and was not robust enough to support the general ledger requirements The company stopped the effort and incurred a 1500.000 USD loss on the cost of the software.
This year, the Director of Finance requested that a team investigate the current paper-based time reporting process and recommend solutions. The Director of Finance feels that the Director of Human Resources must be involved as a critical stakeholder The Director of Human Resources is still bitter about the last effort because the process stopped.
During a design review meeting to discuss the future state, all stakeholders are in agreement except the Director of Human Resources. Who makes the final decision?
After the new report "Customer Sales by Date" was deployed last week, the sales team is now unable to generate the previously existing report "Consolidated Sales by Customer, " which is causing customer dissatisfaction.
What could the business analyst (BA) have assessed to prevent this situation?
A national branch of a global company is struggling to improve business processes of its Public and Government Affairs (PGA) department. To work with external stakeholders effectively, PGA employees need to collect, manage, and exchange a vast amount of information. Complex cases involve collaboration of many employees from different departments. The ability to share information and to coordinate corresponding activities is crucial for the company's growth plans. Their current tools and practices do not serve the purpose well. The existing system, which was deployed a couple of years ago, has only a few active users. The majority of PGA employees avoid using it because the system is hard to use and lacks needed functionality. Consequently, available information is mostly unstructured and stored either locally or on a shared network drive. Some of the information exists only in a paper form.
The branch's PGA head, who sponsors the project, wants to implement a configurable solution that two other branches successfully deployed several months ago. Both deployments were done by three solution
consultants, who will be available to assist in the project. They will be responsible for tailoring the solution to PGA needs, as well as for training the PGA staff. With their help, the sponsor plans to complete the project in approximately three months.
The solution consultants reside in another country 7 hours ahead of the rest of the project team. They will be available part-time, but are planning two one-week long trips to the PGA central office to conduct initial training and to participate in the final deployment of the system into production. The consultants, in turn, expect a business analyst (BA) to assist in collecting necessary data and defining customization requirements.
What should define the timing of business analysis work in this project?
A very large insurer of General Liability and Property Damage insurance has an upward trend of increased claims over the past 5 years.
The Risk Control Area for that company has just completed a 12 month Pilot of a new improved Risk Control Site.
The purpose of the site is to help their customers manage their exposures and ideally prevent them from having claims There were 100 customers that were part of the Pilot that represented 25 different industries. The business goals were to increase use of the site and provide tools to help customer awareness of their exposures, so that they may reduce existing exposures and ultimately reduce claims.
The sites Features were as follows:
* Improvements to the search engine to all customers to search for articles, tools and services on the site
* A checklist function that allow customer to create their own unique Checklists or utilize a sample provided by ABC company to use daily, weekly etc for an area of their facility.
* A promotion feature - where Risk preventing Articles, and tools on the site are marketed toward a customer.
* A profile section allowing for Customer Name, Address and contact Phone number.
Alter the 12 month pilot the business sponsor received an assessment of what was working and what was not. The Assessment of the pilot revealed overall site activity had significantly increased, however only 5% of the time the promotions were viewed. And the most shocking was that total claims increased by nearly 20% for these 100 customers during the pilot period. The business sponsor was perplexed as he had an expectation of reduced claims and at least for 30% viewing of promotions since the project team had spent a lot of careful time and effort on this feature. A BA was assigned to do further analysis regarding the low use of the promotions and why claims were not being reduced.
Regarding the use of promotions the BA looked into other similar companies to see what they did differently to get their customer to look at their promotions. The BA found that similar companies had promotions that targeted the industry the customer was in so it was more relevant to them and they were more interested to view the promotion. In addition the BA sent out a survey to all 100 pilot customers asking probing questions about what they thought of the site and if they felt it had decreased their exposure to risk sufficiently. The Survey responses came back with raving positive comments and providing examples of how the site had been helping in the reduction of claims from the customer's perspective. In addition the survey also revealed insight that the customers found the promotion often irrelevant to their industry.
The BA asked for a dump of all documentation of the 1000 claims that were filed over the 12 month pilot period. The BA found the nearly 90% of the claim filed were all in one region of the country and were all for property damage related to several severe winter storms in the region and the claims were nearly all unavoidable by the customers. The BA brought all this analysis back to the business sponsor and made the recommendation to the business sponsor to require the customer to select 1 of 25 industries in their profile. This would in turn allow for the ability to show industry specific promotions and promote search results relative to a customer's industry to be sorted at the top giving the customer a more personalized experience.
What was the business sponsor looking to validate about the use of promotions?
A business analyst (BA) is working on a payment system (PS) implementation. A set of systems which should interact with a new system has been identified. The business analyst defined that a user with role of "Supervisor" in the PS must pass a two-factor authentication before an execution of the functions: "Change system parameters" and "Set up new supervisor." A user must have the role of "Supervisor" to use the standard functions "Send mail notification" or "Send SMS notification".
The BA defined the following use cases:
•"Change system parameters"
•"Setup new supervisor"
•"Send mail notification"
•"Send SMS notification"
•"Send notification"
•"Pass a two-factor authentication"
The BA wants to create a Use Case diagram.
What standard relationship should be defined between "Change system parameters", "Setup new supervisor" and "Pass a two-factor authentication"?
A business analyst (BA) is working on a payment system (PS) implementation. A set of systems which should interact with a new system has been identified. The business analyst defined that a user with role of "Supervisor" in the PS must pass a two-factor authentication before an execution of the functions: "Change system parameters" and "Set up new supervisor." A user must have the role of "Supervisor" to use the standard functions "Send mail notification" or "Send SMS notification".
The BA defined the following use cases:
•"Change system parameters"
•"Setup new supervisor"
•"Send mail notification"
•"Send SMS notification"
•"Send notification"
•"Pass a two-factor authentication"
The BA wants to create a Use Case diagram.
Which standard relationship should be defined between "Setup new supervisor" and "Send notification?
The business analyst (BA) is not having great success scheduling stakeholder meetings. Stakeholders say they are too busy or there are higher priority meetings on their calendars. The BA is concerned, knowing that stakeholder availability, attitude, and willingness to engage will impact the timeliness of project delivery as well as the.
A project is implemented using a predictive approach. Unfortunately, a lot of change requests (CR) have been raised. A project manager (PM), who should approve each change request, is overworked.
What could the business analyst (BA) propose to make things better?
An organization is trying to streamline its current processes to improve performance and reduce costs. A business analyst (BA) conducted a process improvement workshop and identified the following issues as the top three items to be addressed:
1: There are multiple teams to define systems, functionality, and content in many instances, multiple teams are defining the same functionalities while other functionalities are not being defined at all leading to unclear understanding of business requirements.
2: Product specification forms are published each year. A comparison tool is used to evaluate specification differences between yearly releases; but does not adequately identify changes between versions and needs to be improved.
3: Training consists of a new team member shadowing a seasoned team member. There are no written training materials or formal training sources therefore training is inconsistent and not meeting the needs of the organization.
What analysis approach must the BA use to determine changes required to address the training needs?
A health insurance provider undertakes enhancements to its mobile application platform and finalizes the following capabilities as part of the scope of the next release:
I.Ability to integrate online maps and global positioning system (GPS) technology with the mobile application in real time to display location of service providers in the subscriber's vicinity that participate in the subscriber's plan network.
II.Ability for the subscriber to lookup the service providers by specifying either a postal code or a search area radius in miles.
III.Ability for the subscriber to initiate the download of fee information for one or more service providers in a single request.
Through requirements workshops the business analyst elicits the following detailed business requirements:
1.The company's mobile application platform must support real time integration with the following third party systems:
A ) GPS System
B ) Postal Code Validation
2.The service providers available for selection must participate in the subscriber's medical plan network as of the current system date.
3.The map display shall highlight the boundary of the search area with a dotted yellow line.
4.The extent and shape of the search area shall be determined based on one of the following user choices:
A ) Postal code – Subscriber location acquired from GPS shall be used to determine and populate the related postal code as the default postal code with options for the user to change the postal code.
B ) Radius for the search area around the subscriber's location, that will have default value of 5 miles. The radius can be changed by the subscriber with a maximum range of 50 miles.
5.Subscriber shall be able to select one of the options above and supply corresponding input.
6.System shall validate the user input and display appropriate error messages if invalid.
7.Based on the inputs and the plan of the subscriber, the system shall retrieve information for the participating service providers that are located within the designated search area.
8.System shall display a map including visual markers to indicate locations of the service providers in the top half of the device screen and a list of the same service providers in the bottom half of the device screen.
9.The list of service providers shall include the Name, Phone Number and Street Address.
10.If the subscriber specified the radius or retained the default postal code for the search area, the list shall additionally include the approximate driving distance in miles from the subscriber's last registered location and the list shall be sorted in the ascending order of the driving distance.
11.The subscriber shall be able to select a service provider either from the list or from the map and download a document that contains the name, contact telephone, email address, fax number and the fee schedule for the covered services applicable to the subscriber's plan.
Which of the following characteristics is violated by requirement 5?
A company with a big information technology (IT) department has hired a lead business analyst (BA) to enhance its business analysis practices. The lead BA discovers that sponsors are not satisfied with project outcomes. Developers complain about incomplete, ambiguous, and changing requirements. All stakeholders, including project managers, are blaming long cycles of analysis for the delays. The business analysts, in turn, feel overwhelmed with the number of projects and frustrated by the lack of collaboration from reviewers of their deliverables. All of the evidence is anecdotal and none of the groups could strongly substantiate their opinions.
The lead BA wants the BAs to report anticipated and actual completion dates for their deliverables, as well as the time spent on planned and unplanned activities. What is the lead BA trying to do by analyzing the results of such measurements?
As part of identifying an enterprise's capability to adopt a potential solution, a business analyst (BA) is reviewing existing processes and tools within the enterprise for their ability to adapt to a new solution.
Which of the following assessments is the BA performing?
A business analyst (BA) elicits requirements for the sales order processing of multiple product lines. Elicitation reveals that the business processes for the sales orders of most products follow similar activity patterns that have been established over a number of years. Some of the new proposed seasonal products, however, will necessitate major variations in the process flow of some departments. The seasonal products are likely to be different every year. The business needs to carefully adapt its business practices so that the significant but seasonal variations in some of the business processes for the new products are handled adequately without disrupting the processes for the other established products.
Which of the following approaches must the BA take to manage the requirements for sales order processing in the long term?
When determining the success criteria for an initiative a business analyst (BA) engages end users in order to understand what they would define is an effective solution. What two types of data will the end men need to perform the evaluation?
Company A has been engaged to provided solution software to Company B as part of a combined service offering to Company C.
The initiative requires a sub project for Companies A and B learn Company Cs statutory requirements, a sub project for Company A to write custom functionality for the solution, and a sub project for Company B to develop infrastructure and support for the solution as well as the main project of implementation and cutover from Company Cs current data processing solution to the service from Company B, How does the business analyst (BA) assign requirements to the various solution components to ensure all objectives are met?
What is the time difference in days between the shortest and longest implementation?
An insurance company wants to implement a business intelligence solution to consolidate data from various different internal system to provide a better understanding of their customer base.
A business analysis (BA) is engaged to put together a tender (bid) to be sent to various business intelligence providers and implementation partners. Among other information the business analysis requests the following:
* Licensing costs for year 0 based on needing 1 Central processing Unit (CPU) license
* Licensing costs for specific user types such as Report Creators Online Analytical Process (OLAO) user and Power users
* Predicted licensing costs for renewing in Years 1 and 2
* Full implementation costs
After reviewing the received vendor responses the project team shortlists the candidates to 3 and the BA structures the received information as follows:
The Insurance company has a maximum bucket of $310,000 for the entire to implementation and operation over the first three years. Which vendor or vendors meet that criterion?
A business analyst (BA) on a project is in the process of validating requirements and finds that there is a high degree of uncertainty related 10 one of the assumptions being true. The BA adds the assumption to the risk register and performs a fun risk analysis to handle this situation. What type of strategy is in place if the organization is risk-averse?
A business analyst (BA) is working on an initiative to decommission a legacy system and has discovered the requirement ‘’Ability to view policies created m the legacy system for a period of 6 months. ’’How should the BA classify the requirement based on the requirements classification schema?
Manufacturer 0 has received a merger proposal from Manufacturer K There is concern among the senior management of Manufacturer O that regulations could shift in the future, prompting Manufacturer K to move headquarters elsewhere and close operations at the current Manufacturer O site. In assessing the proposal limitations and as part of identifying enterprise limitations, a culture assessment is completed. As part of this work, what else would the BA perform?
A business analyst (BA) finds that the solution service level agreement (SLA) cannot be met m one out of five identified scenarios. is there 4 a dependency on a requirement which is a part of a future release. How should the BA approach the solution limitation?
What kind of analysis must the BA do to determine if one of the systems is better suited to be modified and upgraded?
The business analyst (BA) works in a global company and the majority of stakeholders are located in different countries The BA already explained the core requirements during the initial meetings. However due to the time zone differences it has been cumbersome to organize further meetings. What method should the BA use so the stakeholders can review the document before final approval?
The project manager wants to have the requirements analysis phase approved and asks the business analyst (BA) if this is possible The BA wants to ensure that the requirements package
A business analyst (BA) assigned to a project has been asked to implement regulatory requirements based on priority. What type of traceability relationship can the BA use to find an the solution components that need to be implemented?
An innovative pizza restaurant announces a new pizza topping each week. Once advertised, the new topping on the regular dough constitutes the sole pizza type offered during the week. No other pizza toppings are offered.
Which of the following processes is a strong candidate to be addressed while planning for requirements reuse?
Which of the following processes measures the maturity level of the security program?
Which of the following is derived from a schedule model to meet the project execution plan and achieve management approval for use as a baseline?
The objective of a solution implemented was to increase the number of customer calls resolved per hour.
When using basic statistical sampling concepts, what does the business analyst (BA) need to consider?
Which of the following is the process of developing a document that formally authorizes a project or a phase?
Which of the following software development life cycles is a methodology that divides the project into phases, and the project manager focuses on control of time, cost, and scope?
A sports wristwatch product manufacturer wants to add a blood sugar monitoring toolkit to the watch. Market research has confirmed that the most profitable segment of the manufacturer’s target customer is looking for this feature. The business analyst (BA) worked with the product owner to finalize the set of requirements and design options and then defined multiple approaches for implementing the feature. At this point, the solutions' team agreed that they were unable to accurately assess the merits of each of the proposed solutions.
What is the possible reason?
A business analyst (BA) has completed the prioritization of requirements with various risk-averse stakeholder groups. Several requirements conflict with a regulatory requirement that, if not implemented, will result in a fine from a regulatory body.
What should the BA do?
Which of the following defines how the project scope should be created, executed, monitored and controlled, and then validated?
Whatare timeless events that show progress in the project.
These are typically achieved at the end of phase in the project lifecycle.
Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
A large company has thousands of geographically dispersed employees and dozens of IT systems. Multiple business analysts (BAs) work in parallel on various requirements with different stakeholders. When considered in isolation, the requirements look meaningful and valuable to those who approved them. However, when it comes to implementation, some of the requirements appear to be contradicting each other. A lead BA recognizes that adding some traceability information would help uncover such conflicts early in the process.
To what should the BA trace the requirements?
A business analyst (BA) has engaged various groups from across the organization to define the business opportunity a potential project will address. The BA must consolidate the information collected from the groups.
The BA should ensure the business needs.
A project's change in scope is assessed and a newly assigned business analyst (BA) is unsure how to communicate the findings and final decision to the wider stakeholder group.
In which of the following can the BA find this information?
Which of the following charts is described in the statement below?
"It shows the causes of a certain event. A common use of this diagram is to identify potential factors causing an overall effect. It helps identify causal factors and contributing causes."
Which of the following techniques is used to test customer acceptance of the solution and to measure marketplace demand?
Which of the following types of elicitation allows each stakeholder to freely discuss their role in a particular process?
A business analyst (BA) at a regional bank has recently been assigned to assist on a project to expand into new markets. The chief executive officer (CEO) envisions the bank as a national brand and has asked the chief financial officer (CFO) to monitor project progress closely. The project manager (PM) has asked the BAs on the team to recommend an appropriate business analysis approach.
Based on the nature of the project and the industry, which approach should they recommend?
A business analyst (BA) plans to hold a workshop next week to elicit requirements for a project. In an informal conversation, another employee mentioned that one of the attendees is likely to be unhappy about the project's impact on their work.
Which of the following techniques will the BA use to avoid disrupting the workshop?
Which of the following quantitative risk analysis techniques relies on experience and past data to compute the probability and impact of risks on project objectives?
A business analyst (BA) is defining the decision-making process for changes raised during a project and wants to understand the decision making authorities within the company.
What might the BA do to gather this information?
A new project has to implement a cyber security release in China, Italy, Germany, the United States, and Canada. The project is a $5 million initiative and must 'go live' in production in all countries on the same day and time to be effective.
Which of the approaches mentioned is suitable for this project based on the size and complexity?
Certified Business Analysis Professional | CBAP Questions Answers | CBAP Test Prep | Certified Business Analysis Professional (CBAP) Designation Questions PDF | CBAP Online Exam | CBAP Practice Test | CBAP PDF | CBAP Test Questions | CBAP Study Material | CBAP Exam Preparation | CBAP Valid Dumps | CBAP Real Questions | Certified Business Analysis Professional CBAP Exam Questions