AD0-E908 Adobe Workfront Core Developer Professional Questions and Answers

Questions 4

One of the most requested connections for Adobe Workfront is to Outlook.

How does the Workfront for Outlook integration enhance the user experience? (Choose two.)

Options:

A.

Users can log time via the Workfront add-in for Outlook via 0365.

B.

Users can update existing project, task, or issues with information from an email.

C.

Users can create a Workfront request based on an email within Outlook.

D.

Users can export Workfront custom dashboards to Outlook recipients.

Buy Now
Questions 5

In which scenario would an administrator use a request queue to resolve a business need?

Options:

A.

Reviewers need a way to accept changes to work in progress.

B.

A larger team needs a way to approve timesheet requests.

C.

A team needs to control the flow of work requests into the department.

Buy Now
Questions 6

An engineering team works with an outside vendor who occasionally needs to review and approve documents in Workfront Proof. Which built-in access level would be assigned to the vendor9

Options:

A.

External User

B.

Contributor

C.

Standard

Buy Now
Questions 7

A designer notices that no tasks associated with a specific project appear on their timesheet. The project owner verified that the designer is assigned to several tasks and that the tasks occur during the week of the current timesheet

Which setting can cause this experience?

Options:

A.

Task assignees must be given contribute access to a project in order for the tasks to automatically appear

B.

A projects status must equate to Current in order for its tasks and issues to automatically appear on timesheets.

C.

All predecessors for a tasks must be complete before they will appear on a timesheet

Buy Now
Questions 8

A System Administrator would like to export all of the calculated custom fields and the associated custom expressions from their Workfront instance to an excel file so that they can create a data dictionary for better governance of their custom data.

How would a System Administrator achieve this?

Options:

A.

Use Kick Starts to export Custom Data to Excel

B.

Create a Parameter report filtered to Parameter Type = Calculated and export to Excel

C.

Go to the Custom Forms area of Workfront in the setup panel and export all fields to Excel

Buy Now
Questions 9

A team has just created a new project template. Before making the template active, the team needs to ensure that users have access to use the template and the projects created from the template.

Which two items must be configured to achieve this requirement? (Choose two.)

Options:

A.

Project Sharing

B.

Template Sharing

C.

Template Group

D.

Team Sharing

Buy Now
Questions 10

A Workfront developer is tasked with building a new custom form to collect project requests. The form will display different sets of options based on different selections, which requires the use of display logic and skip logic in the form.

What are two considerations the developer should take into account when building the conditional logic in the form? (Choose two.)

Options:

A.

When copying an old form with display logic or skip logic, the logic is not copied to the new custom form.

B.

When editing objects in bulk, the custom fields display in the Edit objects box. excluding the fields that are skipped or hidden

C.

Custom fields not included in a display logic statement show on a custom form by default.

D.

Skip logic does not work with a widget or section break in the form

Buy Now
Questions 11

To which two objects in Workfront can a dashboard be added in the left navigation? (Choose two.)

Options:

A.

Portfolio

B.

Timesheet

C.

Project

D.

Calendar

Buy Now
Questions 12

What functionality allows users to build effective reporting visualizations with increased visibility and flexible layout options?

Options:

A.

Canvas Layouts

B.

Canvas Widgets

C.

Canvas Dashboards

Buy Now
Questions 13

A client requires that employees account for any "breaks" during their day in order to report on utilization. How would a System Administrator configure this requirement?

Options:

A.

Create an option for Users to comment on their weekly Timesheet for total 'Break* time.

B.

Create a "Break" General Hour Type to the User's Timesheet Profile.

C.

Create a 'Break" Timesheet Profile and assign all Users.

Buy Now
Questions 14

Where in the standard report builder can a person use a Wildcard?

Options:

A.

Filter

B.

Chart

C.

Grouping

Buy Now
Questions 15

A customer has a set of users who need to review and approve proof assets associated with projects. The approvals always need to route to the users' team for feedback before being sent to their manager.

What needs to be set up in the system to support this consistent review and approval process?

Options:

A.

Create an automated workflow template with two stages for the team and manager to be used with uploaded assets

B.

Create a global two-stage approval process with the team and manager added in separate stages

C.

Create a proof approval associated to a task in the project template assigned to the team and manager

Buy Now
Questions 16

A customer wants to use custom statuses to move a project's tasks through different process stages. Not every user in the system needs to use these custom statuses.

What must an admin-level user do to support this customer requirement?

Options:

A.

Create custom statuses associated with the users' Status Settings in their profile.

B.

Create custom statuses in the Setup area for the Group associated with the projects.

C.

Create a Group utilizing Agile functionality and custom statuses on the Storyboard

Buy Now
Questions 17

An Adobe Workfront System Administrator has been asked to configure timesheet profiles that generate automatically and are sent to managers for approval.

Which two elements of timesheet profiles need to be configured to accomplish this accurately? (Choose two.)

Options:

A.

Specify time interval of automatic timesheet generation (i.e., weekly)

B.

Set approver field to Their Manager"

C.

Provide detailed description of the timesheet profile

D.

Specify projects to appear on the timesheet

Buy Now
Questions 18

A task includes an approval requiring a lead designers approval decision before it can be completed. What action will trigger the approval by the lead designer?

Options:

A.

Request a document approval from the lead designer

B.

Change the task status

C.

Assign a lead designer to the task

Buy Now
Questions 19

A project manager wants to track specific types of issues on a project along with additional custom fields for each type. What is one way to accomplish this requirement?

Options:

A.

Create a custom Issue Type field and add display logic to the Issue View

B.

Enable default issue types for Bug Reports. Change Requests. Issues, and Requests and add display logic for each type

C.

Create a queue on the project and use queue topics to define the issue types and assign custom forms.

Buy Now
Questions 20

Which two actions are necessary for a request queue to be visible in the system? (Choose two.)

Options:

A.

Check the box to publish as a help request queue

B.

Add a routing rule to the queue details

C.

Indicate the default fields to be shown on all requests

D.

Ensure that the queue project is within a status that equates to Current

Buy Now
Questions 21

Which Workfront objects can date effective billing rates be used with?

Options:

A.

Job roles. Users. Groups.

B.

Companies. Users. Job Roles

C.

Users. Teams. Job Roles

Buy Now
Exam Code: AD0-E908
Exam Name: Adobe Workfront Core Developer Professional
Last Update: Nov 23, 2024
Questions: 70
AD0-E908 pdf

AD0-E908 PDF

$25.5  $84.99
AD0-E908 Engine

AD0-E908 Testing Engine

$30  $99.99
AD0-E908 PDF + Engine

AD0-E908 PDF + Testing Engine

$40.5  $134.99