A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.
What Workfront process will effectively facilitate the Project Sponsor review?
Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.
How can the project manager configure this relationship?
A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer's time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.
Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?
An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?
Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.
What may have caused the planned start date of Task 2 to remain the same?
A creative team accesses their assigned work in a My Tasks list report. The team would like to easily see any New tasks highlighted for visibility. How can the project manager accommodate the team’s request?
Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?
A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.
What impact does this have on the project progress status?
When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?
A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.
What should the project manager ask users to do when it comes to completing tasks?
Which project Condition is set when the Progress Status of the project is Behind or At Risk?
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?
A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.
How should the project manager keep these team members apprised of updates?
An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.
In which project area does this information reside?
A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?
Given this information regarding a Task:
Planned Start Date: May 14
Actual Start Date: May 14
Planned Completion Date: May 20
Projected Completion Date: May 22
Percent Complete: 50%
Duration: 5 Days
Planned Hours: 8 Hours
Status: In ProgressIf today's date were May 19, what would be the Task's progress status?